15546 W SATICOY ST 91406
Certificate Information: 15546 W SATICOY ST 91406
- Application / Permit
- 23014-20000-04994
- Plan Check / Job No.
- B23VN16714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 21'-0" X 6'-0" & 10'-6" X 19'-0" ADDITION TO EXISTING SINGLE-FAMILY DWELLING
- Permit Issued
- Issued on 3/18/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 1/5/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/17/2024 | ALEC MOUSAKHANIAN |
| Issued | 3/18/2024 | APPLICANT |
| CofO in Progress | 11/15/2024 | VINCENT HANLEY |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/9/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/10/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/19/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/19/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/26/2024 | Partial Approval | VINCENT HANLEY |
| Insulation | 7/26/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/26/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/20/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/20/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 8/20/2024 | Corrections Issued | DAVID ANDERSON |
| MERV13>=Rough | 8/20/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 8/20/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/30/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/30/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 8/30/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 8/30/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/6/2024 | Approved | VINCENT HANLEY |
| Insulation | 9/6/2024 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/6/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/11/2024 | Approved | VINCENT HANLEY |
| Gas Test | 9/11/2024 | Approved | VINCENT HANLEY |
| Final | 10/16/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/16/2024 | Approved | GREGG CUMMINGS |
| MERV13>=Final | 10/16/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 10/16/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/21/2024 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 10/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 11/12/2024 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 11/12/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/15/2024 | Approved | VINCENT HANLEY |
| Final | 11/15/2024 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 11/15/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/15/2024 | Approved | VINCENT HANLEY |