15546 W SATICOY ST 91406

Certificate Information: 15546 W SATICOY ST 91406

Application / Permit
23014-20000-04994
Plan Check / Job No.
B23VN16714
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 21'-0" X 6'-0" & 10'-6" X 19'-0" ADDITION TO EXISTING SINGLE-FAMILY DWELLING
Permit Issued
Issued on 3/18/2024
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 ALEC MOUSAKHANIAN
Corrections Issued 1/5/2024 ALEC MOUSAKHANIAN
Plan Check Approved 3/17/2024 ALEC MOUSAKHANIAN
Issued 3/18/2024 APPLICANT
CofO in Progress 11/15/2024 VINCENT HANLEY
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/9/2024 COLIN LOREDO
Sewer availability Cleared 2/10/2024 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 2/12/2024 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/19/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/19/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/26/2024 Partial Approval VINCENT HANLEY
Insulation 7/26/2024 Approved VINCENT HANLEY
PLUMBING-Rough 7/26/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 8/20/2024 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 8/20/2024 Corrections Issued DAVID ANDERSON
Green Building Rough 8/20/2024 Corrections Issued DAVID ANDERSON
MERV13>=Rough 8/20/2024 Approved DAVID ANDERSON
PLUMBING-Rough 8/20/2024 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 8/30/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Approved VINCENT HANLEY
Green Building Rough 8/30/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 8/30/2024 Approved VINCENT HANLEY
Shower Pan 8/30/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/6/2024 Approved VINCENT HANLEY
Green Building Rough 9/6/2024 Approved VINCENT HANLEY
Insulation 9/6/2024 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 9/6/2024 Approved VINCENT HANLEY
Drywall Nailing 9/11/2024 Approved VINCENT HANLEY
Gas Test 9/11/2024 Approved VINCENT HANLEY
Final 10/16/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 10/16/2024 Approved GREGG CUMMINGS
MERV13>=Final 10/16/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 10/16/2024 Not Ready for Inspection GREGG CUMMINGS
Final 10/21/2024 Corrections Issued GREGG CUMMINGS
Smoke Detectors 10/21/2024 Not Ready for Inspection GREGG CUMMINGS
Final 11/12/2024 Corrections Issued VINCENT HANLEY
Smoke Detectors 11/12/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 11/15/2024 Approved VINCENT HANLEY
Final 11/15/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 11/15/2024 Approved VINCENT HANLEY
PLUMBING-Final 11/15/2024 Approved VINCENT HANLEY