18736 W HART ST 91335
Certificate Information: 18736 W HART ST 91335
- Application / Permit
- 23014-20000-04990
- Plan Check / Job No.
- B23VN16710
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. (N) Rear rec room addition to (E) SFD and attached garage
- Permit Issued
- Issued on 7/24/2024
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2023 | JOHNPAUL ISIP |
| Corrections Issued | 12/13/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/28/2024 | EDWIN ESPIN |
| Plan Check Approved | 7/23/2024 | JOHNPAUL ISIP |
| Issued | 7/24/2024 | APPLICANT |
| CofO in Progress | 4/20/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 6/2/2026 | JOHN JANSON |
| Permit Finaled | 6/2/2026 | JOHN JANSON |
| CofO Issued | 6/2/2026 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/15/2023 | EDGAR ALCARAZ |
| ZI | Cleared | 12/18/2023 | NELSON RODRIGUEZ |
| Low Impact Development (LID) | Cleared | 5/21/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/28/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/28/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2025 | Partial Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/22/2025 | Partial Approval | ARUTYUN MADATYAN |
| Underground Mechanical | 5/9/2025 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 5/13/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Sewer | 5/16/2025 | Approved | SCOTT SOBEL |
| Underground Mechanical | 5/16/2025 | Approved | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 5/28/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 5/29/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 8/22/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 8/22/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/22/2025 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 8/22/2025 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 8/27/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/15/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 9/15/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 9/15/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 10/15/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 1/7/2026 | No Access for Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 1/14/2026 | Approved | ARUTYUN MADATYAN |
| Final | 4/9/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 4/9/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 4/9/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/20/2026 | Approved | ARUTYUN MADATYAN |
| Final | 4/20/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 4/20/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 4/20/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/20/2026 | Approved | ARUTYUN MADATYAN |