657 E 90TH ST 90002
Certificate Information: 657 E 90TH ST 90002
- Application / Permit
- 23014-20000-04973
- Plan Check / Job No.
- B23VN16680
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: 16'-9" X 24'-3" ADDITION TO (E) SFD, ALL WORK PER WFPP NFPA 13-D FIRE SPRINKLERES REQUIRED THROUGH OUT
- Permit Issued
- Issued on 6/19/2024
- Issuing Office
- Current Status
- Issued on 6/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/9/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/12/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/16/2024 | LUISANGEL VALENZUELA |
| Issued | 6/19/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/22/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | JEANIE LAM |
| Sewer availability | Cleared | 6/11/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/17/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/17/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/26/2024 | Partial Inspection | DAVID FEILER |
| Underground Mechanical | 7/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/5/2024 | Partial Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/17/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/17/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/31/2024 | Partial Approval | JOSH MEISTER |
| Shower Pan | 11/14/2024 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 11/19/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 11/19/2024 | Approved | MICHAEL LEWIS |
| Insulation | 11/25/2024 | Corrections Issued | JOSH MEISTER |
| Insulation | 11/27/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 12/4/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/6/2025 | Approved | ANTHONY RAMOS |
| Final | 3/6/2025 | Corrections Issued | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 3/6/2025 | Approved | JOHN QUINTANILLA |
| Final | 3/13/2025 | Corrections Issued | JOHN QUINTANILLA |