814 W 28TH ST 90007

Certificate Information: 814 W 28TH ST 90007

Application / Permit
23014-20000-04970
Plan Check / Job No.
B23VN16665
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(11) Sorority House
Work Description
*eplan*PROPOSED ADDITION OF DINING ROOM, STORAGE, EXCERCISE ROOM
Permit Issued
Issued on 6/23/2025
Issuing Office
Current Status
Issued on 6/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 SINA KHOSRAVI
Assigned to Zoning Architect 12/21/2023 SINA KHOSRAVI
Corrections Issued 1/8/2024 SINA KHOSRAVI
Quality Review Completed 1/12/2024 GARO TELMI
Applicant returned to address corrections 4/1/2024 SINA KHOSRAVI
Applicant returned to address corrections 5/13/2024 SINA KHOSRAVI
Applicant returned to address corrections 12/11/2024 SINA KHOSRAVI
Applicant returned to address corrections 3/28/2025 SINA KHOSRAVI
Applicant returned to address corrections 5/7/2025 SINA KHOSRAVI
Applicant returned to address corrections 5/22/2025 SINA KHOSRAVI
Applicant returned to address corrections 6/4/2025 SINA KHOSRAVI
Plan Check Approved 6/10/2025 SINA KHOSRAVI
Issued 6/23/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 4/11/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 4/24/2024 JUSTIN BICOL
Historic Resource Verification Cleared 7/2/2024 RAFAEL FONTES
ZI Cleared 7/8/2024 JASON CHAN
Redevelopment Project Area Cleared 9/19/2024 YASMINE BASHIRI
Green Code Cleared 11/19/2024 MICHAEL AYERS
DAS Clearance Cleared 2/18/2025 Shangqin Xie
Low Impact Development (LID) Cleared 3/6/2025 ERNEST TSE
Fire Marshal Fire Life Safety Cleared 3/13/2025 FIRE DEPARTMENT
Roof/Waste drainage to street Cleared 4/5/2025 JOHN LIN
Sewer availability Cleared 4/7/2025 JOHN LIN

Contact Information

Architect Ro,, Insong Curtis; Lic. No.: C16843 447 LAGUNA RD      PASADENA, CA 91105
Contractor Atelier Development Company Inc; Lic. No.: 842591-B       ,
Engineer Astourian,, Sevag Gary; Lic. No.: S5245 2575 LAMBERT DR      PASADENA, CA 91107

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2025 Not Ready for Inspection BARRY HACHE
Pre-Inspection 7/22/2025 Partial Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 8/7/2025 Approved RONALD JIMENEZ
Footing/Foundation/Slab 8/7/2025 Approved RONALD JIMENEZ
METHANE-Barrier 8/7/2025 Approved RONALD JIMENEZ
METHANE-Subgrade 8/7/2025 Approved RONALD JIMENEZ
Deputy Reinf. Concrete 8/8/2025 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Partial Approval ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval ALFREDO LOPEZ
Interior/Exterior Lathing 10/31/2025 Not Ready for Inspection ALFREDO LOPEZ
Insulation 11/4/2025 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 11/4/2025 Partial Approval ALFREDO LOPEZ
Insulation 11/10/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 12/5/2025 Partial Approval ALFREDO LOPEZ
Interior/Exterior Lathing 12/19/2025 Not Ready for Inspection DARRYL ARNOLD
T-Bar Ceiling 4/3/2026 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 4/7/2026 Partial Approval REGINA MENDEZ