20442 W SCHOENBORN ST 91306
Certificate Information: 20442 W SCHOENBORN ST 91306
- Application / Permit
- 23014-20000-04921
- Plan Check / Job No.
- B23VN16519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 35'-6" x 20'-0" TO THE (E) 18'-0" x 20'-0" RECREATION ROOM AND CONVERT IT INTO A NEW 1070 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/8/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 2/15/2024 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 3/6/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/8/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/19/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/23/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/12/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/17/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/25/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/12/2024 | LUISANGEL VALENZUELA |
| Issued | 5/13/2024 | APPLICANT |
| CofO in Progress | 7/17/2025 | JEFFREY HARTLINE |
| No Progress | 10/1/2025 | HENRY KIM |
| CofO in Progress | 10/1/2025 | HENRY KIM |
| Permit Finaled | 10/16/2025 | JOHN JANSON |
| Permit Finaled | 10/16/2025 | JOHN JANSON |
| CofO Issued | 10/16/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/18/2023 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 2/5/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/20/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/20/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 5/20/2024 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/20/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 6/28/2024 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/28/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/16/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/16/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/16/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/16/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/16/2024 | Approved | CHRIS CHRISTENSEN |
| Sewer | 7/16/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/19/2024 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/23/2024 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 7/25/2024 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 7/29/2024 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/29/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| ELECTRICAL-Final | 1/24/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 1/24/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/24/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Service/Power Release | 1/24/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/31/2025 | Approved | JEFFREY HARTLINE |
| Final | 1/31/2025 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 1/31/2025 | Approved | JEFFREY HARTLINE |
| Green Building Final | 1/31/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 1/31/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 1/31/2025 | Approved | JEFFREY HARTLINE |
| Final | 7/17/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 7/17/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 8/29/2025 | Corrections Issued | JEFFREY HARTLINE |