7507 N LASAINE AVE 91406

Certificate Information: 7507 N LASAINE AVE 91406

Application / Permit
23014-20000-04908
Plan Check / Job No.
B23VN16476
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12'-0" X 34'-0" COVERED PATIO ADDITION AND FIRE DAMAGE REPAIR TO ROOF OF EXISTING MASTER BEDROOM, UNDERPIN PORTION OF EXISTING FOUNDATION, REPLACE DOORS AND WINDOWS PER PLAN, AND REMODEL EXISTING BATHROOM - PER ENGINEER
Permit Issued
Issued on 12/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 DANIEL ABRAMYAN
Corrections Issued 12/1/2023 DANIEL ABRAMYAN
Issued 12/5/2023 APPLICANT
CofO in Progress 12/17/2025 JOAQUIN GREENOUGH
Permit Finaled 12/17/2025 RUBEN SALAS
CofO Issued 12/17/2025 RUBEN SALAS
Permit Finaled 12/17/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/2/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/4/2023 COLIN LOREDO

Contact Information

Contractor Tri Tech Restoration & Construction Co Inc; Lic. No.: 501801-B 3301 N SAN FERNANDO BLVD      BURBANK, CA 91504
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/13/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 2/13/2024 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/18/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/18/2024 Corrections Issued RAUL OLAGI
Special/Order Compliance 3/18/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/26/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 3/26/2024 Not Ready for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 4/1/2024 Approved JOHN COLEMAN
PLUMBING-Rough 4/1/2024 Partial Approval JOHN COLEMAN
Deputy Drilled-In Anchors 5/16/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 5/31/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 5/31/2024 Approved SALVADOR MARTINEZ
PLUMBING-Rough 5/31/2024 Approved SALVADOR MARTINEZ
Wood Frame 5/31/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/4/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 6/4/2024 Approved SALVADOR MARTINEZ
Green Building Rough 6/4/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 6/4/2024 Approved SALVADOR MARTINEZ
Wood Frame 6/4/2024 Approved SALVADOR MARTINEZ
Gas Test 6/21/2024 Approved SALVADOR MARTINEZ
Insulation 6/21/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 6/21/2024 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 7/1/2024 Partial Approval SALVADOR MARTINEZ
Green Building Rough 7/1/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 7/8/2024 Approved SALVADOR MARTINEZ
Pre-Inspection 11/4/2024 Approved SALVADOR MARTINEZ
Final 3/26/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 3/26/2025 Partial Inspection SALVADOR MARTINEZ
PLUMBING-Final 3/26/2025 Conditional Approval SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 3/26/2025 Partial Inspection SALVADOR MARTINEZ
ELECTRICAL-Final 7/15/2025 Approved SALVADOR MARTINEZ
HVAC-Final 7/15/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 7/15/2025 Approved SALVADOR MARTINEZ
Final 12/17/2025 OK to Issue CofO JOAQUIN GREENOUGH
Green Building Final 12/17/2025 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 12/17/2025 Approved JOAQUIN GREENOUGH