17202 W HART ST 91406
Certificate Information: 17202 W HART ST 91406
- Application / Permit
- 23014-20000-04883
- Plan Check / Job No.
- B23VN16408
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Propose addition of 11' 2" x 37' and conversion of ALQ to SB9 to create a new duplex, and demo of existing 7' 6" x 37' 2" covered patio. All work done per WFPP.
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | NAREG ATARIAN |
| Corrections Issued | 12/21/2023 | NAREG ATARIAN |
| Quality Review Completed | 12/22/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 12/28/2023 | APPLICANT |
| Plan Check Approved | 1/11/2024 | NAREG ATARIAN |
| Plan Check Approved | 1/11/2024 | NAREG ATARIAN |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 7/9/2025 | JON MCHUGH |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/29/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/29/2023 | EDGAR ALCARAZ |
| Watercourse | Cleared | 12/29/2023 | EDGAR ALCARAZ |
| Senate Bill 9 | Cleared | 1/2/2024 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/21/2024 | Conditional Approval | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 8/22/2024 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 8/23/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 8/29/2024 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/6/2024 | Approved | JON MCHUGH |
| Wood Frame | 9/25/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 10/11/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 10/11/2024 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | JON MCHUGH |
| Green Building Rough | 10/23/2024 | Approved | JON MCHUGH |
| Insulation | 10/23/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/23/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 10/29/2024 | Approved | ALEXANDER HANDY |
| Final | 12/18/2024 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 12/18/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 12/18/2024 | Approved | MORRIS JACKSON |
| Final | 3/21/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/8/2025 | Corrections Issued | JON MCHUGH |
| Final | 5/16/2025 | Partial Approval | JON MCHUGH |
| Service/Power Release | 5/16/2025 | Approved | JON MCHUGH |
| Final | 7/9/2025 | OK to Issue CofO | JON MCHUGH |