5001 N BALBOA BLVD 91316
Certificate Information: 5001 N BALBOA BLVD 91316
- Application / Permit
- 23014-20000-04872
- Plan Check / Job No.
- B23VN16359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- IRR. SHAPED ADDITION (495 SF) AND CONVERT (E) FIRE STATION TO (N) OFFICE FOR COMMUNITY CENTER & RESTRIPE (E) PARKING AREA
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | SEAN SHAHMIRI |
| Assigned to Zoning Architect | 12/8/2023 | SEAN SHAHMIRI |
| Corrections Issued | 12/13/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 12/13/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/13/2023 | APPLICANT |
| Green Plans Picked Up | 12/15/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 12/21/2023 | APPLICANT |
| Plan Check Approved | 12/27/2024 | RAPHAEL ROSAS |
| Issued | 1/3/2025 | APPLICANT |
| CofO in Progress | 12/4/2025 | JEFFREY DURAN |
| Permit Finaled | 12/4/2025 | JEFFREY DURAN |
| CofO Issued | 12/4/2025 | JEFFREY DURAN |
| Permit Finaled | 12/4/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Highway dedication | Cleared | 7/29/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/30/2024 | LEE GUILBEAUX |
| Watercourse | Cleared | 7/30/2024 | LEE GUILBEAUX |
| City owned building/parcel | Cleared | 7/31/2024 | SEAN SHAHMIRI |
| ZA Case | Cleared | 8/1/2024 | BRENNEN OBETO |
| ZI | Cleared | 8/1/2024 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2024 | LEE GUILBEAUX |
| Green Code | Cleared | 8/27/2024 | MICHAEL AYERS |
| DAS Clearance | Cleared | 9/23/2024 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 9/23/2024 | CARLOS RAMIREZ |
| "Q" conditions | Cleared | 12/18/2024 | NATHAN ROMINE |
| CPC | Cleared | 12/18/2024 | NATHAN ROMINE |
| Zoning Plan Check | Cleared | 12/19/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Nazerian Group The; Lic. No.: 787198-B | 17514 VENTURA BLVD SUITE #204 ENCINO, CA 91316 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2025 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 2/24/2025 | Not Ready for Inspection | GREGORY POMISH |
| Protected Tree Letter | 2/25/2025 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 3/6/2025 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 3/10/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Not Ready for Inspection | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 5/20/2025 | Partial Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 5/20/2025 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 5/20/2025 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 5/22/2025 | Partial Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 5/22/2025 | Partial Approval | GREGORY POMISH |
| Wood Frame | 5/22/2025 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 5/27/2025 | Partial Inspection | GREGORY POMISH |
| Insulation | 5/29/2025 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 6/3/2025 | Approved | KENNETH ROBERTS |
| Green Building Rough | 6/3/2025 | Approved | KENNETH ROBERTS |
| T-Bar Ceiling | 7/23/2025 | Not Ready for Inspection | GREGORY POMISH |
| T-Bar Ceiling | 7/30/2025 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 8/1/2025 | Approved | GREGORY POMISH |
| Footing/Foundation/Slab | 8/8/2025 | Partial Approval | JEFFREY DURAN |
| Reinforced Masonry Frame | 8/18/2025 | Approved | GREGORY POMISH |
| Final | 11/7/2025 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 11/7/2025 | Approved | ANDREW DORSO |
| Green Building Final | 11/7/2025 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 11/7/2025 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 11/7/2025 | Approved | ANDREW DORSO |
| Final | 11/20/2025 | OK to Issue CofO | ANDREW DORSO |
| Smoke Detectors | 11/20/2025 | Approved | ANDREW DORSO |