5061-5063 N CARTWRIGHT AVE 91601
Certificate Information: 5061-5063 N CARTWRIGHT AVE 91601
- Application / Permit
- 23014-20000-04856
- Plan Check / Job No.
- B23VN16277
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- eplan. 1st AND 2nd FLOOR ADDTITION TO (E) 1-STORY DUPLEX WITH ATTACHED GARAGE TO HAVE NEW ATTACHED ADU PER LAMC 12.22 A.33 (c) AND (e) ON TOP.
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Current Status
- Issued on 8/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/8/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/26/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/1/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/8/2024 | MAHNAZ NOURHASHEMI |
| Issued | 8/9/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 1/31/2024 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 3/5/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/14/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 4/4/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/4/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Dolphin Construction Inc; Lic. No.: 890521-B | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/30/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 9/4/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/4/2024 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 1/29/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 1/29/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 3/3/2025 | No Access for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/4/2025 | Partial Approval | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 4/14/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 4/14/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/14/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 4/23/2025 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 4/23/2025 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 4/24/2025 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 4/24/2025 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 5/1/2025 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 5/1/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/1/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/6/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 5/6/2025 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 5/13/2025 | Approved | JOSE AVILA |
| Insulation | 5/13/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 5/14/2025 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 5/15/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/20/2025 | Approved | JOSE AVILA |
| Shower Pan | 5/22/2025 | Approved | JOSE AVILA |
| Green Building Rough | 9/3/2025 | Approved | JOSE AVILA |
| Pre-Inspection | 9/3/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/16/2025 | Corrections Issued | JOSE AVILA |
| Gas Test | 9/16/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/25/2025 | Approved | JOSE AVILA |
| Gas Test | 9/25/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 9/25/2025 | Approved | JOSE AVILA |
| Final | 1/26/2026 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/26/2026 | Approved | JOSE AVILA |
| HVAC-Final | 1/26/2026 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 1/26/2026 | Approved | JOSE AVILA |
| Service/Power Release | 2/2/2026 | Approved | JOSE AVILA |