4243 N FARMDALE AVE 91604

Certificate Information: 4243 N FARMDALE AVE 91604

Application / Permit
23014-20000-04854
Plan Check / Job No.
B23VN16270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION & REMODEL TO (E) SFD
Permit Issued
Issued on 7/11/2024
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 CARLOS MONTES
Corrections Issued 12/5/2023 CARLOS MONTES
Quality Review Completed 12/8/2023 GARO TELMI
Applicant returned to address corrections 4/2/2024 CARLOS MONTES
Applicant returned to address corrections 5/31/2024 CARLOS MONTES
Plan Check Approved 7/10/2024 CARLOS MONTES
Issued 7/11/2024 APPLICANT
CofO in Progress 9/5/2025 JAVIER RAMOS JR
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/19/2023 CARLOS RAMIREZ
Sewer availability Cleared 12/19/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/20/2023 CARLOS RAMIREZ
ZI Cleared 12/20/2023 MATHEW QUAN

Contact Information

Contractor Mancilla'S Construction Inc; Lic. No.: 1073745-B       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/1/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/16/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/16/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/23/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 1/23/2025 Partial Inspection CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 1/23/2025 Partial Inspection CHRISTOPHER ROJAS
Insulation 1/28/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 2/20/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 2/20/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 2/20/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 2/20/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 2/20/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 2/20/2025 Approved CHRISTOPHER ROJAS
Shower Pan 2/20/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/27/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 8/22/2025 Approved JAVIER RAMOS JR
Final 8/22/2025 Partial Approval JAVIER RAMOS JR
Green Building Final 8/22/2025 Approved JAVIER RAMOS JR
HVAC-Final 8/22/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 8/22/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/22/2025 Approved JAVIER RAMOS JR
Final 9/4/2025 OK to Issue CofO JAVIER RAMOS JR