Conversion of 1-story Existing Garage (20' x 20') with a (20' x 5') Addition to a Single Family Dwelling per SB9. All Work per Wood Frame Prescriptive Provisions. NFPA 13D Sprinklers Throughout.
Permit Issued
Issued on 2/23/2024
Issuing Office
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 VAHAN JIVALAGIAN
Corrections Issued 12/9/2023 VAHAN JIVALAGIAN
Quality Review Completed 12/13/2023 OMID HEDAYAT
Building Plans Picked Up 12/18/2023 APPLICANT
Plan Check Approved 2/23/2024 VAHAN JIVALAGIAN
Issued 2/23/2024 APPLICANT
CofO in Progress 6/27/2024 VINCENT HANLEY
Permit Finaled 7/3/2024 RUBEN SALAS
CofO Issued 7/3/2024 RUBEN SALAS
Permit Finaled 7/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/27/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/27/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/28/2023 CARLOS AGUILERA
Sewer availability Cleared 12/28/2023 CARLOS AGUILERA
Senate Bill 9 Cleared 2/5/2024 ASHLEY RODARTE
Miscellaneous Cleared 2/21/2024 SUSAN WONG
Hold Cleared 3/6/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/11/2024 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 3/11/2024 Corrections Issued GREGG CUMMINGS
Special/Order Compliance 3/11/2024 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 3/12/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 3/12/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/19/2024 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 4/2/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Corrections Issued KIRK SANDERS
Green Building Rough 4/2/2024 Not Ready for Inspection KIRK SANDERS
Rough-Elec/Plmb/HVAC 4/2/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 4/12/2024 Partial Approval KIRK SANDERS
Rough-Elec/Plmb/HVAC 4/12/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 4/17/2024 Corrections Issued GREGG CUMMINGS
Insulation 4/17/2024 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 4/17/2024 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 4/17/2024 Approved GREGG CUMMINGS
Shower Pan 4/17/2024 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 5/1/2024 Approved MATTHEW NELSON
Green Building Rough 5/1/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 5/2/2024 Corrections Issued KIRK SANDERS
Insulation 5/2/2024 Approved KIRK SANDERS
Underground Mechanical 5/2/2024 Partial Approval KIRK SANDERS
Drywall Nailing 5/6/2024 Approved WILLIAM WREN
ELECTRICAL-Final 5/21/2024 Approved VINCENT HANLEY
Final 5/21/2024 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 5/21/2024 Approved VINCENT HANLEY
Green Building Final 5/21/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/21/2024 SGSOV Not Required VINCENT HANLEY
Smoke Detectors 5/21/2024 Approved VINCENT HANLEY
Final 5/24/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 5/30/2024 Approved VINCENT HANLEY
Final 5/30/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 5/30/2024 Approved VINCENT HANLEY
PLUMBING-Final 5/30/2024 Approved VINCENT HANLEY
Final 6/27/2024 OK to Issue CofO VINCENT HANLEY