8944 N MONOGRAM AVE 91343

Certificate Information: 8944 N MONOGRAM AVE 91343

Application / Permit
23014-20000-04833
Plan Check / Job No.
B23VN16179
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition to existing S.F.D. and conversion of existing attached patio to study room.
Permit Issued
Issued on 12/14/2023
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/29/2023 CAROLEAN BASMA
Corrections Issued 11/30/2023 CAROLEAN BASMA
Applicant returned to address corrections 12/11/2023 CAROLEAN BASMA
Plan Check Approved 12/13/2023 CAROLEAN BASMA
Issued 12/14/2023 APPLICANT
CofO in Progress 6/17/2024 RAUL OLAGI
CofO Issued 7/2/2024 RUBEN SALAS
Permit Finaled 7/2/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/30/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 12/5/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311
Engineer Nazarians,, Harmick; Lic. No.: NA91232       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/9/2024 Conditional Approval DAVID MATSON
PLUMBING-Rough 2/12/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 3/5/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 3/5/2024 Corrections Issued JOHN COLEMAN
HVAC-Rough 3/5/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 3/5/2024 Corrections Issued JOHN COLEMAN
Deputy Wood Construction 3/8/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/14/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 3/14/2024 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 3/14/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 3/19/2024 Approved RAUL OLAGI
HVAC-Rough 3/19/2024 Approved RAUL OLAGI
Insulation 3/19/2024 Approved RAUL OLAGI
PLUMBING-Rough 3/19/2024 Approved RAUL OLAGI
Drywall Nailing 3/28/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 3/28/2024 Approved RAUL OLAGI
Shower Pan 3/28/2024 Approved RAUL OLAGI
Final 5/20/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 5/20/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 5/20/2024 Approved RAUL OLAGI
Final 6/17/2024 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Approved RAUL OLAGI