7913 N FULTON AVE 91605

Certificate Information: 7913 N FULTON AVE 91605

Application / Permit
23014-20000-04831
Plan Check / Job No.
B23VN16177
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20'x20' GARAGE WITH 31' x 18'-6" ADDITION INTO A (N) IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 2/27/2024
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 MIROOSH KHACHATOORIAN
Corrections Issued 12/2/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/6/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/6/2024 ISIS ARGUETA
Plan Check Approved 2/27/2024 ALFRED RAMIREZ
Issued 2/27/2024 APPLICANT
CofO in Progress 8/15/2025 VINCENT HANLEY
Permit Finaled 8/29/2025 RUBEN SALAS
CofO Issued 8/29/2025 RUBEN SALAS
Permit Finaled 8/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/6/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/6/2023 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 12/27/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 1/4/2024 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/30/2024 Partial Approval SALVADOR MARTINEZ
Deputy Reinf. Concrete 8/1/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 8/2/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 8/2/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 8/30/2024 Partial Approval VINCENT HANLEY
Sewer 8/30/2024 Approved VINCENT HANLEY
Underground Mechanical 8/30/2024 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 9/4/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 9/5/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 9/5/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Approved VINCENT HANLEY
HVAC-Rough 9/5/2024 Approved VINCENT HANLEY
PLUMBING-Rough 9/5/2024 Approved VINCENT HANLEY
Insulation 9/16/2024 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 9/16/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 9/18/2024 Approved VINCENT HANLEY
Green Building Rough 9/18/2024 Approved VINCENT HANLEY
Insulation 9/18/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/18/2024 Partial Approval VINCENT HANLEY
Drywall Nailing 9/23/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/23/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 3/19/2025 Corrections Issued VINCENT HANLEY
Final 3/19/2025 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 3/19/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/19/2025 Corrections Issued VINCENT HANLEY
Smoke Detectors 3/19/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 5/23/2025 Approved VINCENT HANLEY
Final 5/23/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 5/23/2025 Approved VINCENT HANLEY
PLUMBING-Final 5/23/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 8/15/2025 Approved VINCENT HANLEY
Final 8/15/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 8/15/2025 Approved VINCENT HANLEY
PLUMBING-Final 8/15/2025 Approved VINCENT HANLEY