16113 W SEPTO ST 91343
Certificate Information: 16113 W SEPTO ST 91343
- Application / Permit
- 23014-20000-04823
- Plan Check / Job No.
- B23VN16162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 17'-8" X 27'-10" IRREGULAR SHAPED ADDITION AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 12/4/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 4/26/2024 | DANIEL ABRAMYAN |
| Issued | 5/2/2024 | APPLICANT |
| CofO in Progress | 10/8/2025 | CHRISTOPHER ROJAS |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2023 | GABRIELLA TORRES |
| Roof/Waste drainage to street | Cleared | 12/6/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 12/11/2023 | GABRIELLA TORRES |
| Grading Pre-Inspection | Cleared | 12/14/2023 | SERGIO VALENZUELA |
| Construction near power lines | Cleared | 4/24/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/24/2024 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/29/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/29/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/5/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/5/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/5/2024 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 8/9/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/13/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/19/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 8/19/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/27/2024 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 8/27/2024 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/27/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/27/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 9/6/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 12/2/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/2/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/3/2024 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/3/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/3/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/3/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/3/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/21/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 10/8/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |