16113 W SEPTO ST 91343

Certificate Information: 16113 W SEPTO ST 91343

Application / Permit
23014-20000-04823
Plan Check / Job No.
B23VN16162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
17'-8" X 27'-10" IRREGULAR SHAPED ADDITION AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
Permit Issued
Issued on 5/2/2024
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 DANIEL ABRAMYAN
Corrections Issued 12/4/2023 DANIEL ABRAMYAN
Plan Check Approved 4/26/2024 DANIEL ABRAMYAN
Issued 5/2/2024 APPLICANT
CofO in Progress 10/8/2025 CHRISTOPHER ROJAS
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/6/2023 GABRIELLA TORRES
Roof/Waste drainage to street Cleared 12/6/2023 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 12/11/2023 GABRIELLA TORRES
Sewer availability Cleared 12/11/2023 GABRIELLA TORRES
Grading Pre-Inspection Cleared 12/14/2023 SERGIO VALENZUELA
Construction near power lines Cleared 4/24/2024 RIDWAN HARDY
Construction within easement Cleared 4/24/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2024 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 6/24/2024 Approved ROBERT GOLD
BUILDING-Rough-Frame 7/29/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/29/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 7/29/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 8/5/2024 Approved JAVIER RAMOS JR
Insulation 8/5/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 8/5/2024 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 8/9/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Approved JAVIER RAMOS JR
Insulation 8/13/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/19/2024 No Access for Inspection ARUTYUN MADATYAN
HVAC-Rough 8/19/2024 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 8/19/2024 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 8/27/2024 Partial Approval JAVIER RAMOS JR
HVAC-Rough 8/27/2024 Partial Inspection JAVIER RAMOS JR
Insulation 8/27/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/27/2024 Approved JAVIER RAMOS JR
Shower Pan 8/27/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/6/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 9/6/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 12/2/2024 Approved MICHEL ABAJAN
PLUMBING-Final 12/2/2024 Approved MICHEL ABAJAN
HVAC-Final 12/3/2024 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 1/3/2025 Approved JAVIER RAMOS JR
Final 1/3/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/3/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/3/2025 Approved JAVIER RAMOS JR
Final 7/3/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/21/2025 Partial Approval CHRISTOPHER ROJAS
Final 10/8/2025 OK to Issue CofO CHRISTOPHER ROJAS