6325 2/3-3/4 W ORANGE ST 90048

Certificate Information: 6325 2/3-3/4 W ORANGE ST 90048

Application / Permit
23014-20000-04816
Plan Check / Job No.
B23VN16146
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 32'-7" PORTION OF 6-CAR GARAGE AND ADD 4'-11" X 31'-7" AT 1ST FLOOR AND 18'-11" X 39'-7" AT 2ND FLOOR TO CREATE (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). 14'-1" X 18' PORTION OF (E) GARAGE TO REMAIN. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
Issued on 3/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 RAPHAEL ROSAS
Corrections Issued 12/13/2023 RAPHAEL ROSAS
Quality Review Completed 12/15/2023 STEVEN KIM
Building Plans Picked Up 12/20/2023 APPLICANT
Applicant returned to address corrections 9/26/2024 RAPHAEL ROSAS
Applicant returned to address corrections 2/11/2025 RAPHAEL ROSAS
Applicant returned to address corrections 2/20/2025 RAPHAEL ROSAS
Plan Check Approved 2/21/2025 RAPHAEL ROSAS
Issued 3/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/9/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/10/2024 WALLIE JONG
Sewer availability Cleared 1/10/2024 WALLIE JONG
Tenant Habitability Plan Cleared 2/29/2024 RICARDO BOHORQUEZ
"Q" conditions Cleared 3/1/2024 ASHLEY RODARTE
Low Impact Development (LID) Cleared 4/23/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/24/2024 TREVOR QUAN
Construction near power lines Cleared 8/28/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/26/2026 Corrections Issued MICHAEL ALLEN
Underground Mechanical 4/29/2026 Approved WILBER ROSALES
METHANE-Barrier 5/13/2026 Approved WILBER ROSALES
Footing/Foundation/Slab 5/18/2026 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Partial Approval WILBER ROSALES
Footing/Foundation/Slab 6/8/2026 Approved WILBER ROSALES
METHANE-Subgrade 6/8/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 7/7/2026 Not Ready for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/7/2026 Approved WILBER ROSALES
Green Building Rough 7/7/2026 Not Ready for Inspection WILBER ROSALES
METHANE-Rough 7/7/2026 Not Ready for Inspection WILBER ROSALES
Wood Frame 7/7/2026 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Rough 7/8/2026 Approved WILBER ROSALES
HVAC-Rough 7/8/2026 Corrections Issued WILBER ROSALES
PLUMBING-Rough 7/8/2026 Corrections Issued WILBER ROSALES
Gas Test 7/10/2026 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 7/10/2026 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 7/14/2026 Not Ready for Inspection WILBER ROSALES
Green Building Rough 7/14/2026 Approved WILBER ROSALES
HVAC-Rough 7/14/2026 Approved WILBER ROSALES
Insulation 7/14/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 7/14/2026 Partial Approval WILBER ROSALES
METHANE-Rough 7/14/2026 Approved WILBER ROSALES
PLUMBING-Rough 7/14/2026 Approved WILBER ROSALES
Drywall Nailing 7/17/2026 Approved CARLOS MATAMOROS
Green Building Rough 7/17/2026 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/20/2026 Approved ANTHONY EGSON