10424 N QUILL AVE 91040

Certificate Information: 10424 N QUILL AVE 91040

Application / Permit
23014-20000-04811
Plan Check / Job No.
B23VN16139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE TO (N) ADU WITH ADDITION PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 7/29/2024
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/28/2023 JOHNPAUL ISIP
Corrections Issued 11/29/2023 JOHNPAUL ISIP
Plan Check Approved 4/18/2024 DAVID CASTILLO
Issued 7/29/2024 APPLICANT
CofO in Progress 7/5/2025 DAVID ANDERSON
Permit Finaled 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/9/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/11/2024 CARLOS AGUILERA
Sewer availability Cleared 3/11/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/13/2024 SERGIO VALENZUELA
Roof/Waste drainage to street Cleared 4/9/2024 CARLOS AGUILERA
Specific Plan Cleared 4/11/2024 ERICK MARCHENA

Contact Information

Architect The, Connell Group; Lic. No.: BUS5900 4829 PRYTANIA STREET STE 100      NEW ORLEANS, LA 70115
Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/2/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/5/2024 Approved DAVID ANDERSON
PLUMBING-Rough 12/5/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 1/8/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/29/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Partial Approval KEVIN BERBERYAN
HVAC-Rough 1/29/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 1/29/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 2/12/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 2/12/2025 Approved DAVID ANDERSON
Green Building Rough 2/12/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/12/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 2/12/2025 Approved DAVID ANDERSON
Insulation 2/19/2025 Approved DAVID ANDERSON
Drywall Nailing 2/24/2025 Approved MATTHEW NELSON
Shower Pan 2/27/2025 Approved DAVID ANDERSON
Special/Order Compliance 2/27/2025 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 3/10/2025 Approved DAVID ANDERSON
Final 7/3/2025 OK to Issue CofO DAVID ANDERSON
Green Building Final 7/3/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 7/3/2025 Approved DAVID ANDERSON