1641 S POINT VIEW ST 90035
Certificate Information: 1641 S POINT VIEW ST 90035
- Application / Permit
- 23014-20000-04796
- Plan Check / Job No.
- B23VN16095
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION (39' X 32'-7" IRREGULAR SHAPE) TO EXISTING SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 12/9/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 12/13/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 2/13/2024 | APPLICANT |
| Applicant returned to address corrections | 8/20/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 11/26/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 12/4/2024 | VAHAN JIVALAGIAN |
| Issued | 12/4/2024 | APPLICANT |
| CofO in Progress | 1/14/2026 | BRENDAN MORELLI |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
| CofO Issued | 1/14/2026 | DEROLD HAUFF |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 6/13/2024 | LUIS LUVANO |
| Sewer availability | Cleared | 11/15/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 11/27/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/14/2025 | Approved | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 1/15/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 1/15/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 1/15/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 1/15/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 1/29/2025 | Partial Approval | ANTHONY RAMOS |
| PLUMBING-Rough | 1/30/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 1/30/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 6/5/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 6/6/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 6/6/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 6/9/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 6/9/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 6/9/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 6/9/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 7/14/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 7/14/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 7/18/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 7/29/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 8/6/2025 | Approved | DEVON JACKSON |
| ELECTRICAL-Final | 12/3/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 12/3/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 12/3/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/13/2026 | Approved | BRENDAN MORELLI |
| Final | 1/13/2026 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 1/13/2026 | Approved | BRENDAN MORELLI |
| HVAC-Final | 1/13/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 1/13/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 1/13/2026 | Approved | BRENDAN MORELLI |