14322 W COHASSET ST 91405

Certificate Information: 14322 W COHASSET ST 91405

Application / Permit
23014-20000-04795
Plan Check / Job No.
B23VN16094
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 12/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 JEROME MAGAT PALMA
Corrections Issued 12/2/2023 JEROME MAGAT PALMA
Building Plans Picked Up 12/5/2023 APPLICANT
Plan Check Approved 12/7/2023 ISIS ARGUETA
Issued 12/7/2023 APPLICANT
CofO in Progress 11/15/2024 VINCENT HANLEY
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/4/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/4/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/5/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/5/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/16/2024 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 4/19/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 4/19/2024 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 4/19/2024 Partial Approval KIRK SANDERS
Deputy Drilled-In Anchors 4/23/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/23/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 5/15/2024 Not Ready for Inspection VINCENT HANLEY
Sewer 5/15/2024 Approved VINCENT HANLEY
Pre-Inspection 5/20/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 6/4/2024 Partial Approval VINCENT HANLEY
HVAC-Rough 6/11/2024 Approved VINCENT HANLEY
PLUMBING-Rough 6/14/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/28/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Approved VINCENT HANLEY
PLUMBING-Rough 6/28/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/12/2024 Approved GREGG CUMMINGS
Green Building Rough 7/12/2024 Approved GREGG CUMMINGS
Insulation 7/12/2024 Approved GREGG CUMMINGS
Drywall Nailing 7/24/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/6/2024 Approved VINCENT HANLEY
Shower Pan 8/6/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/7/2024 Approved VINCENT HANLEY
Final 10/22/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 10/22/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 10/22/2024 Not Ready for Inspection GREGG CUMMINGS
Final 10/31/2024 Corrections Issued VINCENT HANLEY
Green Building Final 10/31/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 10/31/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 11/7/2024 Approved VINCENT HANLEY
Final 11/7/2024 Partial Approval VINCENT HANLEY
HVAC-Final 11/7/2024 Approved VINCENT HANLEY
PLUMBING-Final 11/7/2024 Approved VINCENT HANLEY
Final 11/15/2024 OK to Issue CofO VINCENT HANLEY