14322 W COHASSET ST 91405
Certificate Information: 14322 W COHASSET ST 91405
- Application / Permit
- 23014-20000-04795
- Plan Check / Job No.
- B23VN16094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 12/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 12/2/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/5/2023 | APPLICANT |
| Plan Check Approved | 12/7/2023 | ISIS ARGUETA |
| Issued | 12/7/2023 | APPLICANT |
| CofO in Progress | 11/15/2024 | VINCENT HANLEY |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/4/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/5/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 4/19/2024 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 4/19/2024 | Partial Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 4/23/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/23/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 5/15/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Sewer | 5/15/2024 | Approved | VINCENT HANLEY |
| Pre-Inspection | 5/20/2024 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 6/4/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 6/11/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/14/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/28/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/28/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 7/12/2024 | Approved | GREGG CUMMINGS |
| Insulation | 7/12/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 7/24/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/6/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 8/6/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/7/2024 | Approved | VINCENT HANLEY |
| Final | 10/22/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/22/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 10/22/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/31/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 10/31/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/31/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 10/31/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/7/2024 | Approved | VINCENT HANLEY |
| Final | 11/7/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Final | 11/7/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/7/2024 | Approved | VINCENT HANLEY |
| Final | 11/15/2024 | OK to Issue CofO | VINCENT HANLEY |