5125 N LEDGE AVE 91601

Certificate Information: 5125 N LEDGE AVE 91601

Application / Permit
23014-20000-04788
Plan Check / Job No.
B23VN16063
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
19'-0" X 14'-0" ADDITION AND CONVERT EXISTING DETACHED RECREATION ROOM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER DESIGN
Permit Issued
Issued on 3/27/2024
Issuing Office
Current Status
CofO Issued on 11/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/28/2023 DANIEL ABRAMYAN
Corrections Issued 11/29/2023 DANIEL ABRAMYAN
Plan Check Approved 3/13/2024 DANIEL ABRAMYAN
Issued 3/27/2024 APPLICANT
CofO in Progress 10/23/2024 ROBERTO PALACIOS-LOPEZ
CofO Issued 11/2/2024 DANIEL ORRANTE
Permit Finaled 11/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/18/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/18/2023 CARLOS AGUILERA
Sewer availability Cleared 12/19/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/12/2024 CARLOS AGUILERA
Construction near power lines Cleared 2/23/2024 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor J&C Retrofit Construction Inc; Lic. No.: 1041138-B 1477 W MARTIN LUTHER KING BLVD      LOS ANGELES, CA 90062

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/22/2024 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/22/2024 Not Ready for Inspection JOHN HAYES
Underground Mechanical 4/22/2024 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 4/24/2024 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/24/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/24/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/21/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/21/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 5/21/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/21/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 5/21/2024 Partial Approval MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 5/21/2024 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/5/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 6/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/11/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/11/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/14/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/18/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/26/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/26/2024 Approved JENNIFER RABUCHIN
Final 9/27/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 9/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/4/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 10/4/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 10/4/2024 Approved MISAEL ESPARZA
Final 10/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Final 10/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/23/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ