2230 1/4 W FARGO ST 90039
Certificate Information: 2230 1/4 W FARGO ST 90039
- Application / Permit
- 23014-20000-04782
- Plan Check / Job No.
- B23VN16043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 16'-9" X 20'-5" ON SECOND FLOOR TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH 16'-9" X 20'-5" ROOFTOP DECK
- Permit Issued
- Issued on 6/11/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | SELLA BENYAMIN |
| Corrections Issued | 12/14/2023 | SELLA BENYAMIN |
| Quality Review Completed | 12/15/2023 | STEVEN KIM |
| Building Plans Picked Up | 12/15/2023 | APPLICANT |
| Plan Check Approved | 6/6/2024 | SELLA BENYAMIN |
| Issued | 6/11/2024 | APPLICANT |
| CofO in Progress | 5/29/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/31/2025 | DEROLD HAUFF |
| CofO Issued | 5/31/2025 | DEROLD HAUFF |
| Permit Finaled | 5/31/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/9/2024 | VASIL MIHALEV |
| Address approval | Cleared | 1/20/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 1/20/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2024 | ARNULFO CHAMU |
| Sewer availability | Cleared | 2/14/2024 | ARNULFO CHAMU |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/1/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/11/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/11/2024 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/28/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 11/6/2024 | Partial Approval | LUIS CASTRO |
| Sewer | 11/6/2024 | Not Ready for Inspection | LUIS CASTRO |
| Underground Mechanical | 11/6/2024 | Partial Approval | LUIS CASTRO |
| Sewer | 11/19/2024 | Approved | HAMIK HARTOUNIAN |
| Deputy Steel/Welding | 12/2/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Steel/Welding | 12/6/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Structural Steel Frame | 1/29/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 2/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/20/2025 | Approved | CRAIG DAVIS |
| HVAC-Rough | 2/20/2025 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/25/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 3/4/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/4/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 3/4/2025 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 3/4/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/7/2025 | Order to Comply Issued | DAVID WILLIAMS |
| Drywall Nailing | 3/17/2025 | Approved | REGINA MENDEZ |
| Gas Test | 3/17/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/17/2025 | Approved | REGINA MENDEZ |
| Final | 5/22/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 5/22/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 5/22/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/22/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 5/29/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 5/29/2025 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 5/29/2025 | Approved | HAMIK HARTOUNIAN |