2230 1/4 W FARGO ST 90039

Certificate Information: 2230 1/4 W FARGO ST 90039

Application / Permit
23014-20000-04782
Plan Check / Job No.
B23VN16043
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 16'-9" X 20'-5" ON SECOND FLOOR TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH 16'-9" X 20'-5" ROOFTOP DECK
Permit Issued
Issued on 6/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 SELLA BENYAMIN
Corrections Issued 12/14/2023 SELLA BENYAMIN
Quality Review Completed 12/15/2023 STEVEN KIM
Building Plans Picked Up 12/15/2023 APPLICANT
Plan Check Approved 6/6/2024 SELLA BENYAMIN
Issued 6/11/2024 APPLICANT
CofO in Progress 5/29/2025 HAMIK HARTOUNIAN
Permit Finaled 5/31/2025 DEROLD HAUFF
CofO Issued 5/31/2025 DEROLD HAUFF
Permit Finaled 5/31/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/9/2024 VASIL MIHALEV
Address approval Cleared 1/20/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 1/20/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/14/2024 ARNULFO CHAMU
Sewer availability Cleared 2/14/2024 ARNULFO CHAMU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/1/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/1/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/4/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/11/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 10/11/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/28/2024 Approved ROY SPAULDING
PLUMBING-Rough 11/6/2024 Partial Approval LUIS CASTRO
Sewer 11/6/2024 Not Ready for Inspection LUIS CASTRO
Underground Mechanical 11/6/2024 Partial Approval LUIS CASTRO
Sewer 11/19/2024 Approved HAMIK HARTOUNIAN
Deputy Steel/Welding 12/2/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Steel/Welding 12/6/2024 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Corrections Issued HAMIK HARTOUNIAN
Structural Steel Frame 1/29/2025 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/20/2025 Approved CRAIG DAVIS
HVAC-Rough 2/20/2025 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/25/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/25/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/4/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 3/4/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/4/2025 Approved HAMIK HARTOUNIAN
MERV13>=Rough 3/4/2025 Approved HAMIK HARTOUNIAN
Shower Pan 3/4/2025 Approved HAMIK HARTOUNIAN
Insulation 3/7/2025 Order to Comply Issued DAVID WILLIAMS
Drywall Nailing 3/17/2025 Approved REGINA MENDEZ
Gas Test 3/17/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 3/17/2025 Approved REGINA MENDEZ
Final 5/22/2025 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 5/22/2025 Partial Inspection HAMIK HARTOUNIAN
MERV13>=Final 5/22/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 5/22/2025 Approved HAMIK HARTOUNIAN
Final 5/29/2025 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 5/29/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 5/29/2025 Approved HAMIK HARTOUNIAN