308 S SYCAMORE AVE 90036
Certificate Information: 308 S SYCAMORE AVE 90036
- Application / Permit
- 23014-20000-04775
- Plan Check / Job No.
- B23VN16025
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/23/2024
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 11/29/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/1/2023 | APPLICANT |
| Applicant returned to address corrections | 7/11/2024 | ANGELICA DAVE |
| Plan Check Approved | 7/23/2024 | ALEC MOUSAKHANIAN |
| Issued | 7/23/2024 | APPLICANT |
| CofO in Progress | 11/19/2025 | JOSH MEISTER |
| No Progress | 11/23/2025 | DEROLD HAUFF |
| CofO in Progress | 11/23/2025 | DEROLD HAUFF |
| No Progress | 11/29/2025 | DEROLD HAUFF |
| CofO in Progress | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2023 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/14/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 12/15/2023 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 4/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/8/2024 | Corrections Issued | RONNIE MINDANAO |
| Pre-Inspection | 9/25/2024 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Inspection | 10/8/2024 | Partial Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/22/2024 | Partial Approval | RONNIE MINDANAO |
| HVAC-Rough | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 10/22/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 10/22/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 3/10/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 3/10/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 3/10/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 3/10/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 3/10/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 3/18/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/7/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 4/15/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/21/2025 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 4/21/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 4/21/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/24/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/24/2025 | Approved | DAVID WILLIAMS |
| Shower Pan | 4/24/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 5/27/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 5/27/2025 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 5/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 5/29/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 8/11/2025 | Approved | RONNIE MINDANAO |
| Final | 10/28/2025 | Partial Inspection | RAUL BARAJAS |
| Green Building Final | 10/28/2025 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/28/2025 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 10/28/2025 | Approved | RAUL BARAJAS |
| Final | 11/4/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | RONNIE MINDANAO |
| Final | 11/18/2025 | OK to Issue CofO | JOSH MEISTER |