11628-11630 N BALBOA BLVD 91344
Certificate Information: 11628-11630 N BALBOA BLVD 91344
- Application / Permit
- 23014-20000-04767
- Plan Check / Job No.
- B23VN15999
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD TO & CONVERT PORTION OF GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2023 | JESSE ARELLANO |
| Corrections Issued | 11/28/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 11/29/2023 | APPLICANT |
| Applicant returned to address corrections | 1/4/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 1/4/2024 | ALEC MOUSAKHANIAN |
| Issued | 1/4/2024 | APPLICANT |
| CofO in Progress | 2/1/2024 | JAVIER RAMOS JR |
| No Progress | 3/5/2024 | ROBERT GOLD |
| CofO in Progress | 3/5/2024 | ROBERT GOLD |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
| CofO Issued | 5/1/2024 | RUBEN SALAS |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 12/19/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/19/2023 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 1/4/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/9/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/12/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/12/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/12/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 1/12/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/12/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 1/12/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/19/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 1/26/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 1/26/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 1/26/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/31/2024 | Approved | JAVIER RAMOS JR |
| Final | 1/31/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 1/31/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 1/31/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 1/31/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/31/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/31/2024 | Approved | JAVIER RAMOS JR |