14334 W COHASSET ST 91405

Certificate Information: 14334 W COHASSET ST 91405

Application / Permit
23014-20000-04745
Plan Check / Job No.
B23VN15923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH 10' X 8' & IRREGULAR SHAPED 25'-9" X 18'-6" ADDITION TO CREATE NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 SERGIO MUNIZ
Corrections Issued 11/25/2023 SERGIO MUNIZ
Building Plans Picked Up 12/1/2023 APPLICANT
Plan Check Approved 1/16/2024 ALEC MOUSAKHANIAN
Issued 3/26/2024 APPLICANT
CofO in Progress 1/30/2025 VINCENT HANLEY
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/2/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 12/2/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/5/2023 COLIN LOREDO
Sewer availability Cleared 12/5/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2024 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 4/1/2024 Partial Inspection DAVID MATSON
PLUMBING-Rough 4/1/2024 Partial Approval DAVID MATSON
Footing/Foundation/Slab 4/2/2024 Approved KIRK SANDERS
Sewer 4/16/2024 Corrections Issued SALVADOR MARTINEZ
Gas Test 4/18/2024 Partial Approval KIRK SANDERS
Sewer 4/18/2024 Approved KIRK SANDERS
Underground Mechanical 4/18/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval WILLIAM WREN
HVAC-Rough 5/3/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 5/6/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 5/6/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 5/6/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 7/12/2024 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/12/2024 Approved GREGG CUMMINGS
HVAC-Rough 7/12/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 7/12/2024 Approved GREGG CUMMINGS
ELECTRICAL-Rough 7/15/2024 Approved VINCENT HANLEY
Wood Frame 7/15/2024 Partial Approval VINCENT HANLEY
Deputy Wood Construction 7/22/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 7/30/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Approved VINCENT HANLEY
Green Building Rough 7/30/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/5/2024 Not Ready for Inspection VINCENT HANLEY
Shower Pan 8/5/2024 Approved VINCENT HANLEY
Insulation 8/6/2024 Corrections Issued VINCENT HANLEY
Insulation 8/7/2024 Approved VINCENT HANLEY
Insulation 8/14/2024 Approved GREGG CUMMINGS
Drywall Nailing 8/19/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 1/15/2025 Approved VINCENT HANLEY
Final 1/15/2025 Corrections Issued VINCENT HANLEY
Green Building Final 1/15/2025 Approved VINCENT HANLEY
HVAC-Final 1/15/2025 Approved VINCENT HANLEY
PLUMBING-Final 1/15/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/15/2025 Approved VINCENT HANLEY
Final 1/30/2025 OK to Issue CofO VINCENT HANLEY