17444 W VALERIO ST 91406

Certificate Information: 17444 W VALERIO ST 91406

Application / Permit
23014-20000-04741
Plan Check / Job No.
B23VN15915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add 16'-4 1/4" x 13'-0" to & convert (e) detached garage into an accessory dwelling unit per LAMC 12.22 A.33 (c)-(d), all work per WFPP
Permit Issued
Issued on 11/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 RAMA DABADGE
Corrections Issued 11/27/2023 RAMA DABADGE
Building Plans Picked Up 1/11/2024 APPLICANT
Applicant returned to address corrections 2/26/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/30/2024 JESSE ARELLANO
Applicant returned to address corrections 11/8/2024 MIROOSH KHACHATOORIAN
Issued 11/15/2024 APPLICANT
CofO in Progress 1/16/2026 GAREN HAYRAPETYAN
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/27/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/27/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/13/2024 CARLOS AGUILERA
Sewer availability Cleared 2/13/2024 CARLOS AGUILERA
Construction near power lines Cleared 11/13/2024 TINA MIRANDA
Construction within easement Cleared 11/13/2024 TINA MIRANDA

Contact Information

Contractor Yaghoubian Construction; Lic. No.: 1090155-B 5445 LINDLEY AVE #31      TARZANA, CA 91356

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2025 Approved GAREN HAYRAPETYAN
Sewer 4/15/2025 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 4/30/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 4/30/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/16/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 5/16/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Corrections Issued MICHAEL CORTEZ
Underground Mechanical 7/11/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 8/7/2025 Approved KEVIN BERBERYAN
HVAC-Rough 8/7/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 8/7/2025 Approved KEVIN BERBERYAN
Insulation 9/11/2025 Not Ready for Inspection WAYNE REGESTER
Interior/Exterior Lathing 9/11/2025 Conditional Approval WAYNE REGESTER
BUILDING-Rough-Frame 9/15/2025 Approved GAREN HAYRAPETYAN
Deputy Wood Construction 9/15/2025 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 9/15/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 9/15/2025 Approved GAREN HAYRAPETYAN
Special/Order Compliance 9/15/2025 Corrections Issued GAREN HAYRAPETYAN
Insulation 9/18/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 9/18/2025 Approved WAYNE REGESTER
Shower Pan 9/18/2025 Approved WAYNE REGESTER
Drywall Nailing 10/1/2025 Approved LOUIS ESCOTO
Underground Mechanical 12/11/2025 Partial Approval GAREN HAYRAPETYAN
Final 12/19/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/19/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 12/19/2025 Approved GAREN HAYRAPETYAN
Final 1/16/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 1/16/2026 Approved GAREN HAYRAPETYAN