9333 N TELFAIR AVE 91352
Certificate Information: 9333 N TELFAIR AVE 91352
- Application / Permit
- 23014-20000-04722
- Plan Check / Job No.
- B23VN15853
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST (400 SQFT) AND 2ND FLOOR (760 SQFT) ADDITION OF AN ADU TO THE EXISTING DETACHED 2-CAR GARAGE PER LAMC 12.22 A.33(c)(d) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/17/2025
- Issuing Office
- Current Status
- Issued on 12/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | SEAN SHAHMIRI |
| Corrections Issued | 11/30/2023 | PETER MOSESIAN |
| Quality Review Completed | 12/4/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/16/2024 | PETER MOSESIAN |
| Plan Check Approved | 11/4/2025 | SEAN SHAHMIRI |
| Plan Check Approved | 12/17/2025 | INTERNET PERMIT |
| Issued | 12/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 4/25/2024 | ROGELIO CORTES |
| ZI | Cleared | 10/18/2024 | NATHAN ROMINE |
| Clean Up Green Up | Cleared | 1/10/2025 | DAVID URITA |
| Private sewage disp. approval | Cleared | 10/16/2025 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 11/19/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Azc Construction Inc; Lic. No.: 1000738-B | , |
| Contractor | L A Construction And Maintenance; Lic. No.: 1000738-B | , |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/22/2026 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 6/24/2026 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 6/24/2026 | Partial Approval | MATTHEW NELSON |