5516 N WILLOW CREST AVE 91601
Certificate Information: 5516 N WILLOW CREST AVE 91601
- Application / Permit
- 23014-20000-04717
- Plan Check / Job No.
- B23VN15838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- SUPPLEMENTAL PERMIT TO 07014-20000-04798 TO EXPAND EX STORAGE RM W/4'X7' ADDN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2023 | MADISON ODELL |
| Corrections Issued | 11/20/2023 | MADISON ODELL |
| Plan Check Approved | 1/22/2024 | HAYATO TSUCHIYA |
| Issued | 1/22/2024 | APPLICANT |
| CofO in Progress | 6/20/2024 | THOMAS WOODS |
| CofO Issued | 7/23/2024 | DAVID JAMES |
| Permit Finaled | 7/23/2024 | DAVID JAMES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/10/2024 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2024 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Drywall Nailing | 1/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Final | 1/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 1/23/2024 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 1/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Green Building Rough | 1/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Smoke Detectors | 1/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| Drywall Nailing | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| Final | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| Green Building Final | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| Green Building Rough | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| Smoke Detectors | 4/23/2024 | No Access for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 4/24/2024 | Not Ready for Inspection | THOMAS WOODS |
| Drywall Nailing | 4/24/2024 | Not Ready for Inspection | THOMAS WOODS |
| Final | 4/24/2024 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 4/24/2024 | Approved | THOMAS WOODS |
| Green Building Final | 4/24/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 4/24/2024 | Not Ready for Inspection | THOMAS WOODS |
| Smoke Detectors | 4/24/2024 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | THOMAS WOODS |
| Drywall Nailing | 5/31/2024 | Approved | THOMAS WOODS |
| Final | 5/31/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 5/31/2024 | Approved | THOMAS WOODS |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | THOMAS WOODS |
| ELECTRICAL-Final | 6/4/2024 | Not Ready for Inspection | THOMAS WOODS |
| Final | 6/4/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 6/4/2024 | Approved | THOMAS WOODS |
| HVAC-Final | 6/4/2024 | Not Ready for Inspection | THOMAS WOODS |
| PLUMBING-Final | 6/4/2024 | Not Ready for Inspection | THOMAS WOODS |
| Smoke Detectors | 6/4/2024 | Approved | THOMAS WOODS |
| METHANE-Final | 6/5/2024 | Not Ready for Inspection | THOMAS WOODS |
| ELECTRICAL-Final | 6/17/2024 | Approved | THOMAS WOODS |
| Final | 6/17/2024 | Not Ready for Inspection | THOMAS WOODS |
| Gas Test | 6/17/2024 | Corrections Issued | THOMAS WOODS |
| ELECTRICAL-Final | 6/20/2024 | Approved | THOMAS WOODS |
| Final | 6/20/2024 | OK to Issue CofO | THOMAS WOODS |
| Gas Test | 6/20/2024 | Approved | THOMAS WOODS |
| HVAC-Final | 6/20/2024 | Approved | THOMAS WOODS |
| PLUMBING-Final | 6/20/2024 | Approved | THOMAS WOODS |