11445 N SKYLAND ROAD 91040
Certificate Information: 11445 N SKYLAND ROAD 91040
- Application / Permit
- 23014-20000-04715
- Plan Check / Job No.
- B23VN15822
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* ADD 4' X 13' TO EXISTING SINGLE FAMILY DWELLING; CONVERT EXISTING 21'-4" X 21'-1" GARAGE TO NEW BEDROOM
- Permit Issued
- Issued on 3/28/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | SELLA BENYAMIN |
| Corrections Issued | 11/30/2023 | SELLA BENYAMIN |
| Quality Review Completed | 12/7/2023 | STEVEN KIM |
| Applicant returned to address corrections | 1/18/2024 | SELLA BENYAMIN |
| Plan Check Approved | 3/27/2025 | SELLA BENYAMIN |
| Issued | 3/28/2025 | APPLICANT |
| CofO in Progress | 6/10/2026 | NICHOLAS TROWBRIDGE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2024 | CARLOS AGUILERA |
| Private sewage disp. approval | Cleared | 5/3/2024 | MICHAEL TEMPLE |
| Private street | Cleared | 3/18/2025 | ALEX VELA |
| Private street | Cleared | 3/18/2025 | ALEX VELA |
| Specific Plan | Cleared | 3/18/2025 | ALEX VELA |
| GPI Written Notices | Cleared | 3/27/2025 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 3/27/2025 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/4/2025 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 4/4/2025 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 4/4/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/8/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 4/8/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 4/8/2025 | Corrections Issued | WILLIAM WREN |
| Insulation | 6/2/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 6/3/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 7/10/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/10/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/10/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | MATTHEW NELSON |
| Insulation | 7/29/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/4/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 8/4/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 8/22/2025 | Approved | WILLIAM WREN |
| Final | 6/3/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 6/3/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 6/5/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Final | 6/8/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |