10781 N BIG BEND AVE 91040
Certificate Information: 10781 N BIG BEND AVE 91040
- Application / Permit
- 23014-20000-04707
- Plan Check / Job No.
- B23VN15785
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. ADDITION (620 SF) AND REMODEL TO EXISTING SFD AND ATTACHED GARAGE. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 1/10/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2023 | ALFREDO JARA |
| Corrections Issued | 11/19/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 1/3/2024 | JASON JANGADA |
| Plan Check Approved | 1/9/2024 | JASON JANGADA |
| Issued | 1/10/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | WILLIAM WREN |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| CofO Issued | 6/3/2025 | RUBEN SALAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Watercourse | Cleared | 11/25/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2023 | BRYAN GODINEZ |
| ZI | Cleared | 11/28/2023 | ASHLEY RODARTE |
| Low Impact Development (LID) | Cleared | 1/2/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/2/2024 | BRYAN GODINEZ |
| GPI Written Notices | Cleared | 1/3/2024 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 1/3/2024 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/1/2024 | Partial Approval | WILLIAM WREN |
| Pre-Inspection | 3/1/2024 | Corrections Issued | WILLIAM WREN |
| Deputy Drilled-In Anchors | 3/6/2024 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 3/6/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 3/11/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 8/2/2024 | No Access for Inspection | MATTHEW NELSON |
| HVAC-Rough | 8/2/2024 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/2/2024 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/7/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 8/7/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/7/2024 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 8/12/2024 | Conditional Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/16/2024 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | WILLIAM WREN |
| Insulation | 8/27/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/13/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 9/13/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 10/25/2024 | Approved | WILLIAM WREN |
| Shower Pan | 10/25/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Ready | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Final | 4/1/2025 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Not Ready | WILLIAM WREN |
| Smoke Detectors | 4/1/2025 | Approved | WILLIAM WREN |
| Final | 4/24/2025 | Conditional Approval | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | WILLIAM WREN |
| Final | 5/1/2025 | Corrections Issued | WILLIAM WREN |
| Final | 5/19/2025 | OK to Issue CofO | WILLIAM WREN |