15113 W LA MAIDA ST 91403

Certificate Information: 15113 W LA MAIDA ST 91403

Application / Permit
23014-20000-04687
Plan Check / Job No.
B23VN15724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 15'-6" X 16'-5" BEDRM/CLOSET/WASHER/DRYER ROOM ADDITION AT REAR PER ARCHITECT'S DESIGN.
Permit Issued
Issued on 1/22/2024
Issuing Office
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 HAYATO TSUCHIYA
Corrections Issued 11/21/2023 HAYATO TSUCHIYA
Building Plans Picked Up 11/22/2023 APPLICANT
Plan Check Approved 12/7/2023 LUISANGEL VALENZUELA
Issued 1/22/2024 APPLICANT
CofO in Progress 6/17/2024 JACK KARGODORIAN
Permit Finaled 6/24/2024 RUBEN SALAS
Permit Finaled 6/24/2024 RUBEN SALAS
CofO Issued 6/24/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/6/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/6/2023 EDGAR ALCARAZ

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Aiden'S Structural Concepts; Lic. No.: 922303-B 13230 BROMONT AVE #111      SYLMAR, CA 91342

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 2/16/2024 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 2/20/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 2/29/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 3/5/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 3/5/2024 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 3/5/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 3/12/2024 Partial Approval THOMAS FINNILA
Green Building Rough 3/12/2024 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 3/12/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 4/1/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/17/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 4/17/2024 Approved THOMAS FINNILA
MERV13>=Rough 4/17/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/23/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 4/24/2024 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 4/24/2024 Approved THOMAS FINNILA
PLUMBING-Rough 4/24/2024 Not Ready for Inspection THOMAS FINNILA
Insulation 4/30/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 5/3/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/6/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 6/6/2024 Approved SALVADOR MARTINEZ
Final 6/6/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 6/6/2024 Approved SALVADOR MARTINEZ
Green Building Final 6/6/2024 Not Ready for Inspection SALVADOR MARTINEZ
MERV13>=Final 6/6/2024 Approved SALVADOR MARTINEZ
PLUMBING-Final 6/6/2024 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 6/6/2024 Corrections Issued SALVADOR MARTINEZ
Final 6/14/2024 OK to Issue CofO JACK KARGODORIAN
Green Building Final 6/14/2024 Approved JACK KARGODORIAN
Smoke Detectors 6/14/2024 Approved JACK KARGODORIAN