649 W 30TH ST 90007

Certificate Information: 649 W 30TH ST 90007

Application / Permit
23014-20000-04680
Plan Check / Job No.
B23VN15699
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 14'3" X 8'6" LAUNDRY ROOM ADDITION TO AN EXISTING 4-UNIT APARTMENT BUILDING, ALL WORK PER ENGINEEERING
Permit Issued
Issued on 2/2/2024
Issuing Office
Current Status
Issued on 2/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/14/2023 APPLICANT
Assigned to Plan Check Engineer 11/17/2023 RARES BODEA
Corrections Issued 11/20/2023 RARES BODEA
Quality Review Completed 11/27/2023 STEVEN KIM
Assigned to Zoning Architect 12/1/2023 RARES BODEA
Applicant returned to address corrections 1/30/2024 RARES BODEA
Plan Check Approved 2/1/2024 RARES BODEA
Issued 2/2/2024 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 11/29/2023 ALEX VELA
ZA Case Cleared 11/29/2023 ALEX VELA
ZI Cleared 11/29/2023 ALEX VELA
Tenant Habitability Plan Cleared 12/7/2023 RICARDO BOHORQUEZ
Low Impact Development (LID) Cleared 12/18/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/19/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 1/9/2024 JUSTIN BICOL
Redevelopment Project Area Cleared 1/9/2024 ELIZABETH GALLARDO
Green Code Cleared 1/18/2024 MICHAEL AYERS
DAS Clearance Cleared 1/22/2024 Shangqin Xie
Zoning Plan Check Cleared 1/30/2024 Shangqin Xie

Contact Information

Architect Badie,, Amin; Lic. No.: NA28846       ,
Contractor A M S Construction; Lic. No.: 992388-B       ,
Contractor Jax J C C Inc; Lic. No.: 992388-B       ,
Engineer Sadeghi,, Hamid M; Lic. No.: C33504 30941 W AGOURA RD 236      WESTLAKE VILLAGE, CA 91361
Engineer Sadeghi,, Hamid M; Lic. No.: NA33504       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/17/2024 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 4/18/2024 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/19/2024 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 6/19/2024 Partial Approval JACOB MYERS
Pre-Inspection 6/20/2024 Partial Approval JACOB MYERS
Green Building Rough 7/30/2024 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Rough 7/30/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 7/30/2024 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 8/8/2024 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Rough 8/8/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 8/8/2024 Partial Inspection ALFREDO LOPEZ
Green Building Rough 8/13/2024 OK to Expire Permit ALFREDO LOPEZ
METHANE-Rough 8/13/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 8/13/2024 Partial Inspection ALFREDO LOPEZ
Insulation 9/4/2024 Not Ready for Inspection ALFREDO LOPEZ
Insulation 9/6/2024 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 9/6/2024 Approved ALFREDO LOPEZ
Drywall Nailing 9/13/2024 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 9/19/2024 Approved ALFREDO LOPEZ
Final 11/7/2024 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 11/7/2024 Approved RONALD JIMENEZ
Green Building Final 11/7/2024 Approved RONALD JIMENEZ
Green Building Rough 11/7/2024 Approved RONALD JIMENEZ
METHANE-Barrier 11/7/2024 Approved RONALD JIMENEZ
METHANE-Final 11/7/2024 Approved RONALD JIMENEZ
METHANE-Rough 11/7/2024 Approved RONALD JIMENEZ
METHANE-Subgrade 11/7/2024 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 11/7/2024 Approved RONALD JIMENEZ
Wood Frame 11/7/2024 Approved RONALD JIMENEZ
Final 1/7/2025 Not Ready for Inspection ALFREDO LOPEZ
Final 1/15/2025 Not Ready for Inspection ALFREDO LOPEZ
Final 9/3/2025 Not Ready for Inspection JEROME BLACKWOOD
Final 9/9/2025 Not Ready for Inspection ALFREDO LOPEZ