7826 W OWENS ST 91040
Certificate Information: 7826 W OWENS ST 91040
- Application / Permit
- 23014-20000-04663
- Plan Check / Job No.
- B23VN15622
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND 20'-3" X 5'-4" IRREGULAR SHAPED ADDITION TO SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 11/18/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/1/2023 | APPLICANT |
| Plan Check Approved | 12/22/2023 | DANIEL ABRAMYAN |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 10/17/2024 | WILLIAM WREN |
| Permit Finaled | 10/25/2024 | DANIEL ORRANTE |
| CofO Issued | 10/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 12/8/2023 | NIKKI ZULUETA |
| Grading Pre-Inspection | Cleared | 12/19/2023 | ADELA MARIANO |
| Watercourse | Cleared | 12/21/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/3/2024 | Partial Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/9/2024 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 1/9/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 1/12/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/17/2024 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 1/17/2024 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/13/2024 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 2/13/2024 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 2/13/2024 | Corrections Issued | WILLIAM WREN |
| Wood Frame | 2/13/2024 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 2/14/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 2/14/2024 | Corrections Issued | WILLIAM WREN |
| Wood Frame | 2/14/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 2/21/2024 | Approved | WILLIAM WREN |
| Insulation | 2/21/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/21/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/22/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 2/26/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 2/26/2024 | Approved | WILLIAM WREN |
| Gas Test | 2/27/2024 | Not Ready for Inspection | WILLIAM WREN |
| Shower Pan | 2/27/2024 | Corrections Issued | WILLIAM WREN |
| Gas Test | 2/29/2024 | Approved | WILLIAM WREN |
| Shower Pan | 2/29/2024 | Not Ready for Inspection | WILLIAM WREN |
| Shower Pan | 3/1/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/11/2024 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 3/18/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/1/2024 | Approved | JACK KARGODORIAN |
| Final | 8/1/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 8/1/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 8/1/2024 | Approved | JACK KARGODORIAN |
| Final | 10/16/2024 | OK to Issue CofO | WILLIAM WREN |