6712-6712 1/2 N ST CLAIR AVE 91606
Certificate Information: 6712-6712 1/2 N ST CLAIR AVE 91606
- Application / Permit
- 23014-20000-04660
- Plan Check / Job No.
- B23VN15618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSE (N) 25'-2"X24'-3" TWO STORY SB 9 UNIT (per SB9 Two-Unit Development Ca Govt Code 65852.21) ADDITION, AND 24'-9"X13'-9" BEDROOM/CLOSET/BATHRM ADDITION TO (E) SFD" TO CREATE A DUPLEX_ ENTIRE BUIDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 6/11/2024
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | DAWN MC NULTY |
| Corrections Issued | 12/13/2023 | DAWN MC NULTY |
| Quality Review Completed | 12/15/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/31/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 6/4/2024 | DAWN MC NULTY |
| Plan Check Approved | 6/10/2024 | DAWN MC NULTY |
| Issued | 6/11/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 12/19/2023 | NATHAN ROMINE |
| Sewer availability | Cleared | 12/19/2023 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 12/28/2023 | NATHAN ROMINE |
| ZI | Cleared | 12/28/2023 | DAVID URITA |
| Low Impact Development (LID) | Cleared | 1/16/2024 | SAMUEL LINN |
| Permit | Cleared | 1/17/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/17/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/18/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 9/27/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/28/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 10/30/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/17/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/4/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/6/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/6/2025 | No Access for Inspection | GAREN HAYRAPETYAN |
| Special/Order Compliance | 2/6/2025 | No Access for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 2/13/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/13/2025 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/7/2025 | Partial Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/12/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 3/18/2025 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 4/1/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/2/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/11/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/16/2025 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/28/2025 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/1/2025 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/29/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 6/10/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 7/23/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/23/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 7/23/2025 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 7/23/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/23/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 8/29/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |