11015 W CALIFA ST 91601
Certificate Information: 11015 W CALIFA ST 91601
- Application / Permit
- 23014-20000-04658
- Plan Check / Job No.
- B23VN15617
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION AND 2-STORY ADDITION TO DETACHED GARAGE FOR ADU WITH INCIDENTAL STORAGE ROOM.
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | JOE VO |
| Corrections Issued | 11/19/2023 | JOE VO |
| Quality Review Completed | 11/22/2023 | GARO TELMI |
| Applicant returned to address corrections | 1/17/2024 | JOE VO |
| Plan Check Approved | 1/27/2025 | JOE VO |
| Issued | 1/28/2025 | APPLICANT |
| CofO in Progress | 12/2/2025 | ROBERTO PALACIOS-LOPEZ |
| No Progress | 2/21/2026 | RAUL OLAGI |
| CofO in Progress | 2/21/2026 | RAUL OLAGI |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
| CofO Issued | 3/12/2026 | RUBEN SALAS |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/18/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 7/23/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/29/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/2/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/9/2025 | JERRY KAO |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chang,, Yeh; Lic. No.: NA6868 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/12/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/24/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/3/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | MICHAEL CORTEZ |
| Rough-Elec/Plmb/HVAC | 6/18/2025 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 6/23/2025 | Corrections Issued | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 6/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/1/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 7/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 7/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 7/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 7/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 7/17/2025 | Approved | MICHAEL CORTEZ |
| Gas Test | 7/17/2025 | Partial Approval | MICHAEL CORTEZ |
| Underground Mechanical | 8/25/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Final | 11/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 11/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/17/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 12/2/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 12/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |