17007 W COTTER PL 91436

Certificate Information: 17007 W COTTER PL 91436

Application / Permit
23014-20000-04646
Plan Check / Job No.
B23VN15574
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION (1049 SQFT) THROUGHOUT EXISTING 1-STORY SINGLE FAMILY DWELLING INCLUDING NEW INTERIOR LAYOUT/BEDROOMS/CONVERT EXISTING ATTACHED GARAGE AND BUILD NEW ATTACHED GARAGE, W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/1/2024
Issuing Office
Valley
Current Status
CofO in Progress on 6/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/13/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 PETER MOSESIAN
Corrections Issued 11/18/2023 PETER MOSESIAN
Quality Review Completed 11/21/2023 OMID HEDAYAT
Building Plans Picked Up 11/22/2023 APPLICANT
Plan Check Approved 2/1/2024 PETER MOSESIAN
Issued 3/1/2024 APPLICANT
CofO in Progress 6/11/2025 THOMAS FINNILA

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/1/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/1/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/1/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/1/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/6/2023 CARLOS AGUILERA
Sewer availability Cleared 12/6/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/16/2024 LAVEON RIDER
Low Impact Development (LID) Cleared 1/24/2024 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 1/24/2024 JOHN LIN

Contact Information

Contractor Oag; Lic. No.: 1101018-B 9712 LIVE OAK AVE      TEMPLE CITY, CA 91780
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2024 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 3/14/2024 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 No Access for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 3/29/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Corrections Issued THOMAS FINNILA
Underground Mechanical 5/20/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval THOMAS FINNILA
PLUMBING-Rough 6/3/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 6/7/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 6/7/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 6/7/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 6/12/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 6/12/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 6/20/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 6/20/2024 Corrections Issued THOMAS FINNILA
HVAC-Rough 6/20/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 6/20/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/27/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 6/27/2024 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 6/27/2024 Not Ready for Inspection THOMAS FINNILA
Wood Frame 6/27/2024 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/1/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 7/3/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 7/3/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/3/2024 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 7/3/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 7/8/2024 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 7/8/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 7/9/2024 Partial Approval THOMAS FINNILA
Insulation 7/18/2024 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 7/18/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 7/30/2024 Partial Approval ALEXANDER HANDY
Interior/Exterior Lathing 7/30/2024 Approved ALEXANDER HANDY
Drywall Nailing 8/8/2024 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 8/28/2024 Partial Approval SCOTT SOBEL
Shower Pan 8/28/2024 Not Ready for Inspection SCOTT SOBEL
Interior/Exterior Lathing 8/29/2024 Partial Approval SCOTT SOBEL
Shower Pan 8/29/2024 Corrections Issued SCOTT SOBEL
Shower Pan 9/4/2024 Approved SCOTT SOBEL
BUILDING-Rough-Frame 11/18/2024 Approved THOMAS FINNILA
Drywall Nailing 11/18/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 11/18/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Approved THOMAS FINNILA
ELECTRICAL-Final 3/19/2025 Approved THOMAS FINNILA
HVAC-Final 3/19/2025 Approved THOMAS FINNILA
PLUMBING-Final 3/19/2025 Approved THOMAS FINNILA
Final 6/10/2025 OK to Issue CofO THOMAS FINNILA
Green Building Final 6/10/2025 Approved THOMAS FINNILA