4150 N FARMDALE AVE 91604

Certificate Information: 4150 N FARMDALE AVE 91604

Application / Permit
23014-20000-04639
Plan Check / Job No.
B23VN15555
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Remove all exterior and interior walls of an existing one story dwelling and except 5 lf at south portion of the lot and build an 55'7" x 39' irregular shaped two story dwelling with attached two car garage , Nfpa-13d fire sprinklers required throughout, all work per engineering
Permit Issued
Issued on 7/11/2024
Issuing Office
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 RARES BODEA
Corrections Issued 11/22/2023 RARES BODEA
Quality Review Completed 11/27/2023 STEVEN KIM
Applicant returned to address corrections 5/6/2024 RARES BODEA
Applicant returned to address corrections 5/8/2024 RARES BODEA
Plan Check Approved 5/10/2024 RARES BODEA
Issued 7/11/2024 APPLICANT
CofO in Progress 5/29/2025 JAVIER RAMOS JR
CofO in Progress 7/8/2025 JUAN VALENZUELA
Permit Finaled 7/30/2025 RUBEN SALAS
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/5/2023 EDGAR ALCARAZ
Permit Cleared 12/5/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/5/2023 EDGAR ALCARAZ
ZI Cleared 12/14/2023 JAZMIN ROQUE
Low Impact Development (LID) Cleared 1/5/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 1/12/2024 EDGAR ALCARAZ
Trees in Parkway Cleared 1/24/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 2/3/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/22/2024 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 8/5/2024 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 8/6/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/12/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/19/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 9/17/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/4/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/15/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/23/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/28/2024 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Partial Inspection MISAEL ESPARZA
Interior/Exterior Lathing 10/28/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 10/28/2024 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Light Gage Steel Frame 10/30/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 10/30/2024 Approved CHRISTOPHER ROJAS
Special/Order Compliance 10/30/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 10/31/2024 Conditional Approval JUAN VALENZUELA
Interior/Exterior Lathing 11/1/2024 Partial Approval CHRISTOPHER ROJAS
Shower Pan 11/5/2024 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 11/8/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 11/8/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 11/8/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/14/2024 Approved CHRISTOPHER ROJAS
Insulation 11/14/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/14/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/19/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Final 5/6/2025 Corrections Issued JAVIER RAMOS JR
Final 5/6/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Final 5/6/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 5/6/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 5/6/2025 Approved JAVIER RAMOS JR
Smoke Detectors 5/6/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/28/2025 Approved JAVIER RAMOS JR
Final 5/28/2025 OK to Issue CofO JAVIER RAMOS JR