11644 W WEDDINGTON ST 91601
Certificate Information: 11644 W WEDDINGTON ST 91601
- Application / Permit
- 23014-20000-04632
- Plan Check / Job No.
- B23VN15541
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING DETACHED GARAGE WITH 10'-0" X 14'-2" ADDITION TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 11/19/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/28/2023 | ALEC MOUSAKHANIAN |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 2/6/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| CofO Issued | 3/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/28/2023 | GABRIELLA TORRES |
| Construction near power lines | Cleared | 12/11/2023 | WALTER RAMIREZ |
| Specific Plan | Cleared | 12/14/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 12/14/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 12/14/2023 | JOANNA MARROQUIN |
| Address approval | Cleared | 12/18/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 12/19/2023 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 7/1/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/15/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/19/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 9/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 9/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/25/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 9/25/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 9/25/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/25/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/30/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/16/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/16/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 10/16/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| Final | 1/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| Final | 1/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/27/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |