623 N ERSKINE DR 90272

Certificate Information: 623 N ERSKINE DR 90272

Application / Permit
23014-20000-04622
Plan Check / Job No.
B23VN15523
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition of 26' x 21' 6" second story ADU per LAMC 12.22 A.33 (c)-(d) above garage with rooftop deck, All work done per engineer.
Permit Issued
Issued on 7/23/2024
Issuing Office
Metro
Current Status
Issued on 7/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 NAREG ATARIAN
Corrections Issued 11/29/2023 NAREG ATARIAN
Quality Review Completed 12/1/2023 OMID HEDAYAT
Building Plans Picked Up 12/6/2023 APPLICANT
Applicant returned to address corrections 5/30/2024 NAREG ATARIAN
Plan Check Approved 6/7/2024 NAREG ATARIAN
Issued 7/23/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/7/2024 DARIN LAM
Coastal Zone Cleared 2/21/2024 BRENNEN OBETO
Mello Bill Cleared 2/21/2024 BRENNEN OBETO
Miscellaneous Cleared 2/21/2024 BRENNEN OBETO
Miscellaneous Cleared 2/21/2024 BRENNEN OBETO
ZA Case Cleared 2/21/2024 BRENNEN OBETO
ZI Cleared 2/21/2024 BRENNEN OBETO
Roof/Waste drainage to street Cleared 3/26/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/11/2024 DARIN LAM
Sewer availability Cleared 4/11/2024 DARIN LAM
Grading Pre-Inspection Cleared 5/30/2024 JOHNNY MIRANDA

Contact Information

Architect Uskert,, Derek Carl; Lic. No.: C32400 PO BOX 403      TAHOE VISTA, CA 96148
Contractor Caribe Construction Inc; Lic. No.: 878090-B 521 S PARISH PLACE      BURBANK, CA 91506
Engineer Lewis,, Richard; Lic. No.: C90522 6044 HALM AVE      LOS ANGELES, CA 90056

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2024 Approved EVAN COOPER
Footing/Foundation/Slab 9/3/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval EVAN COOPER
ELECTRICAL-Rough 11/19/2024 Corrections Issued EVAN COOPER
PLUMBING-Rough 11/19/2024 Approved EVAN COOPER
HVAC-Rough 11/27/2024 Corrections Issued EVAN COOPER
Sewer 11/27/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 12/6/2024 Conditional Approval EVAN COOPER
Insulation 12/23/2024 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 12/23/2024 Corrections Issued KEVIN SARGSYAN