15935 W TULSA ST 91344

Certificate Information: 15935 W TULSA ST 91344

Application / Permit
23014-20000-04618
Plan Check / Job No.
B23VN15514
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT EX. GARAGE TO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d).
Permit Issued
Issued on 3/27/2024
Issuing Office
Valley
Current Status
Issued on 3/27/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/15/2023 SERGIO MUNIZ
Corrections Issued 11/15/2023 SERGIO MUNIZ
Building Plans Picked Up 11/28/2023 APPLICANT
Plan Check Approved 3/27/2024 ROSENDO MEDINA
Issued 3/27/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/3/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/3/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/10/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/10/2024 EDGAR ALCARAZ
Construction near power lines Cleared 2/14/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/7/2025 Conditional Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/12/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 8/12/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/21/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 8/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/11/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 9/11/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/15/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/22/2025 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 11/12/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 11/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 11/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 11/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 11/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/5/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 12/5/2025 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 12/12/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/12/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 12/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 12/12/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 12/12/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/9/2026 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 1/9/2026 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 1/16/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/16/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 1/16/2026 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 1/16/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 1/16/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/12/2026 Approved KEVIN BERBERYAN
Underground Mechanical 3/12/2026 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/9/2026 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 4/9/2026 Approved KEVIN BERBERYAN
Special/Order Compliance 4/9/2026 Corrections Issued KEVIN BERBERYAN