6511 N WHITSETT AVE 91606
Certificate Information: 6511 N WHITSETT AVE 91606
- Application / Permit
- 23014-20000-04606
- Plan Check / Job No.
- B23VN15493
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 8'-0' x 18'-9" ADDITION OF A STORAGE ROOM TO THE (E) GARAGE, ALL WORK PER WFPP
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Current Status
- CofO Issued on 10/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/9/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/31/2024 | ALEC MOUSAKHANIAN |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 9/23/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
| CofO Issued | 10/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/15/2023 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 2/16/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/15/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 8/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Not Ready for Inspection | DAVID MATSON |
| Interior/Exterior Lathing | 8/19/2024 | Corrections Issued | DAVID MATSON |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 9/3/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Final | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/12/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 9/12/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |