12100 N ADELPHIA AVE 91340

Certificate Information: 12100 N ADELPHIA AVE 91340

Application / Permit
23014-20000-04596
Plan Check / Job No.
B23VN15455
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Remodel and addition to the rear of an existing 1-story single-family dwelling with attached garage
Permit Issued
Issued on 12/6/2023
Issuing Office
Current Status
CofO Issued on 7/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2023 APPLICANT
Assigned to Plan Check Engineer 11/13/2023 DANIEL SMILEY
Corrections Issued 11/14/2023 DANIEL SMILEY
Applicant returned to address corrections 11/30/2023 MINA HABILI
Plan Check Approved 12/5/2023 MINA HABILI
No Progress 12/5/2023 MINA HABILI
Plan Check Approved 12/5/2023 MINA HABILI
Issued 12/6/2023 APPLICANT
CofO in Progress 6/18/2024 MICHEL ABAJAN
Permit Finaled 7/5/2024 RUBEN SALAS
CofO Issued 7/5/2024 RUBEN SALAS
Permit Finaled 7/5/2024 RUBEN SALAS

Permit Application Clearance Information

Zoning Information File Cleared 11/17/2023 DANIEL SMILEY
Roof/Waste drainage to street Cleared 11/18/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/20/2023 LEE GUILBEAUX
Sewer availability Cleared 11/20/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/20/2023 LEE GUILBEAUX
Clean Up Green Up Cleared 11/21/2023 BRENNEN OBETO
ZA Case Cleared 11/29/2023 SPENCER WEJROWSKI

Contact Information

Contractor J C D Property Services Inc; Lic. No.: 994393-B       ,
Engineer Pachunuri,, Nalin Kumar; Lic. No.: C78970 21126 INGOMAR CT      CANOGA PARK, CA 91304

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/8/2023 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 12/18/2023 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 12/19/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 1/2/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/8/2024 Corrections Issued MICHEL ABAJAN
Green Building Rough 1/8/2024 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 1/8/2024 Approved MICHEL ABAJAN
Wood Frame 1/8/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 1/23/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/23/2024 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 1/23/2024 Approved MICHEL ABAJAN
HVAC-Rough 1/23/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 1/23/2024 Approved MICHEL ABAJAN
Wood Frame 1/23/2024 Partial Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 1/24/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 1/26/2024 Approved MISAEL ESPARZA
Insulation 1/30/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/30/2024 Approved MICHEL ABAJAN
Drywall Nailing 2/13/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/31/2024 Approved MICHEL ABAJAN
Final 5/31/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 5/31/2024 Approved MICHEL ABAJAN
HVAC-Final 5/31/2024 Approved MICHEL ABAJAN
MERV13>=Final 5/31/2024 Approved MICHEL ABAJAN
PLUMBING-Final 5/31/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 5/31/2024 Approved MICHEL ABAJAN
Final 6/11/2024 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved MICHEL ABAJAN