7000 N BOTHWELL ROAD 91335
Certificate Information: 7000 N BOTHWELL ROAD 91335
- Application / Permit
- 23014-20000-04581
- Plan Check / Job No.
- B23VN15380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ENCLOUSE (E) COVERT PATIO TO LIVING AREA AND ADDITION TO EXISTING SINGLE FAMILY
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- CofO Issued on 8/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | JOSEPH RAFOLS |
| Corrections Issued | 11/14/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 12/12/2023 | JAD BASMA |
| Applicant returned to address corrections | 1/3/2024 | JAD BASMA |
| Applicant returned to address corrections | 1/26/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/6/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/8/2024 | KHUONG TRUONG |
| Plan Check Approved | 4/3/2024 | KHUONG TRUONG |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 7/26/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 8/18/2025 | JOHN JANSON |
| CofO Issued | 8/18/2025 | JOHN JANSON |
| Permit Finaled | 8/18/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/7/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/19/2023 | CARLOS AGUILERA |
| ZI | Cleared | 12/22/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 3/26/2024 | PATRICK LOPEZ |
Contact Information
| Contractor | La Top Builders Inc; Lic. No.: 1077576-B | , |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91202 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/21/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/15/2025 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/4/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/10/2025 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Drywall Nailing | 2/13/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Partial Approval | ARUTYUN MADATYAN |
| Wood Frame | 2/13/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/5/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/21/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/21/2025 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 3/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 4/1/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | ARUTYUN MADATYAN |
| Wood Frame | 4/1/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Insulation | 4/3/2025 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 4/14/2025 | Approved | ARUTYUN MADATYAN |
| Final | 7/8/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 7/8/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 7/8/2025 | Not Ready for Inspection | ROBERT GOLD |
| Final | 7/21/2025 | Partial Approval | ROBERT GOLD |
| Smoke Detectors | 7/21/2025 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 7/25/2025 | Approved | ARUTYUN MADATYAN |
| Final | 7/25/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 7/25/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 7/25/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 7/25/2025 | Approved | ARUTYUN MADATYAN |