19751 W PARTHENIA ST 91324
Certificate Information: 19751 W PARTHENIA ST 91324
- Application / Permit
- 23014-20000-04579
- Plan Check / Job No.
- B23VN15376
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. ADD 10' X 18' ON FIRST FLOOR AND 18' X 30' ON SECOND FLOOR OF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) TO EXISTING DETACHED GARAGE (GARAGE TO REMAIN)
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | SELLA BENYAMIN |
| Corrections Issued | 12/7/2023 | SELLA BENYAMIN |
| Quality Review Completed | 12/11/2023 | STEVEN KIM |
| Plan Check Approved | 2/15/2024 | SELLA BENYAMIN |
| No Progress | 5/14/2024 | SELLA BENYAMIN |
| Plan Check Approved | 5/14/2024 | SELLA BENYAMIN |
| Issued | 5/15/2024 | APPLICANT |
| CofO in Progress | 12/10/2024 | JEFFREY HARTLINE |
| Permit Finaled | 1/2/2025 | JOHN JANSON |
| CofO Issued | 1/2/2025 | JOHN JANSON |
| Permit Finaled | 1/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Hold | Cleared | 12/11/2023 | MARIA VENDIVIL |
| Address approval | Cleared | 12/14/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/15/2023 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/19/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/29/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | L F Country Construction; Lic. No.: 530675-B | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
| Engineer | Youm,, Moung Han; Lic. No.: NA74086 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/24/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 5/24/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 7/3/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 7/3/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/17/2024 | Corrections Issued | JEFFREY HARTLINE |
| Gas Test | 7/17/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 7/17/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 7/17/2024 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 7/17/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 7/25/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 8/1/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Final | 9/27/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 9/27/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/27/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Service/Power Release | 9/27/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Rec and Parks Fee Memo | 9/27/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/9/2024 | Approved | JEFFREY HARTLINE |
| Final | 10/9/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 10/9/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 11/4/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| Service/Power Release | 11/4/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 11/4/2024 | Approved | JEFFREY HARTLINE |
| Final | 12/9/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 12/9/2024 | Approved | JEFFREY HARTLINE |