10748 W CALIFA ST 91601
Certificate Information: 10748 W CALIFA ST 91601
- Application / Permit
- 23014-20000-04574
- Plan Check / Job No.
- B23VN13996
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 5' X 17'-2" TO (E) GARAGE AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED PATIO COVER ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/8/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 11/8/2023 | STEVEN KIM |
| Applicant returned to address corrections | 12/27/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/22/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 12/16/2024 | JOSE AVILA |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/27/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/27/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2024 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 5/9/2024 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 7/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 7/11/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 7/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 9/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 9/25/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 9/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/25/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 10/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/22/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 11/22/2024 | Approved | MATTHEW NELSON |
| Final | 11/22/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 11/22/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 11/22/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 11/22/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 11/22/2024 | Approved | MATTHEW NELSON |
| Final | 12/13/2024 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 12/13/2024 | Approved | JOSE AVILA |