13250 1/2 W MERCER ST 91331

Certificate Information: 13250 1/2 W MERCER ST 91331

Application / Permit
23014-20000-04493
Plan Check / Job No.
B23VN15053
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH ADDITION TO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) , WORK DONE PER WFPP
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2023 APPLICANT
Assigned to Plan Check Engineer 11/7/2023 KHUONG TRUONG
Corrections Issued 11/8/2023 KHUONG TRUONG
Applicant returned to address corrections 1/24/2024 KELVIN CHUONG
Applicant returned to address corrections 5/30/2024 SELLA BENYAMIN
Plan Check Approved 6/24/2024 CARLOS MONTES
Issued 6/24/2024 APPLICANT
CofO in Progress 12/11/2025 MICHEL ABAJAN
No Progress 12/18/2025 MICHEL ABAJAN
CofO in Progress 12/23/2025 RAUL OLAGI
CofO in Progress 12/23/2025 RAUL OLAGI
CofO Issued 12/23/2025 RUBEN SALAS
Permit Finaled 12/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/15/2023 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 11/15/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/16/2023 BRYAN GODINEZ
Sewer availability Cleared 11/16/2023 BRYAN GODINEZ
Construction near power lines Cleared 1/22/2024 RIDWAN HARDY
Permit Cleared 2/6/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/24/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 2/24/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 3/10/2025 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 3/10/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/12/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/12/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/18/2025 Approved MICHEL ABAJAN
Green Building Rough 3/18/2025 Approved MICHEL ABAJAN
HVAC-Rough 3/18/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/18/2025 Approved MICHEL ABAJAN
Insulation 3/24/2025 Conditional Approval MICHEL ABAJAN
Drywall Nailing 4/1/2025 Approved MICHEL ABAJAN
Underground Mechanical 5/16/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/4/2025 Approved MICHEL ABAJAN
Final 12/4/2025 OK to Issue CofO MICHEL ABAJAN
Green Building Final 12/4/2025 Approved MICHEL ABAJAN
HVAC-Final 12/4/2025 Approved MICHEL ABAJAN
PLUMBING-Final 12/4/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/4/2025 Approved MICHEL ABAJAN