(N) 31'-10" x 18'-7"ADDITION FOR MASTER BEDROOM AND (N) 6'-9" X 6'-6" ADDITION FOR LAUNDRY ROOM, INTERIOR REMODEL TO (E) SFD TO REMOVE BEDROOM, ENLARGE DINING ROOM, AND REMODEL (E) BEDROOMS. WORK PER ENGINEERING. " NFPA - 13D FIRE SPRINKLERS REQUIRED THROUGH- OUT"
Permit Issued
Issued on 2/8/2024
Issuing Office
Current Status
CofO Issued on 3/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2023 APPLICANT
Assigned to Plan Check Engineer 11/8/2023 ISIS ARGUETA
Corrections Issued 11/8/2023 ISIS ARGUETA
Building Plans Picked Up 11/13/2023 APPLICANT
Issued 2/8/2024 APPLICANT
CofO in Progress 2/28/2025 LUIS CASTRO
Permit Finaled 3/2/2025 DEROLD HAUFF
Permit Finaled 3/2/2025 DEROLD HAUFF
CofO Issued 3/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/29/2023 DAVID LOPEZ
Low Impact Development (LID) Cleared 1/11/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 1/19/2024 AMBER CAMPBELL
HPOZ Cleared 1/30/2024 DANIEL MATA

Contact Information

Contractor Homefix Construction Inc; Lic. No.: 1066244-B 6225 BABCOCK AVE      NORTH HOLLYWOOD, CA 91606
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Partial Approval JUSTIN HAWLEY
Underground Mechanical 3/14/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 4/12/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Rough 4/12/2024 Approved JUSTIN HAWLEY
HVAC-Rough 4/12/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 4/12/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 4/19/2024 Partial Approval JUSTIN HAWLEY
Green Building Rough 4/19/2024 Approved JUSTIN HAWLEY
HVAC-Rough 4/19/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/19/2024 Approved JUSTIN HAWLEY
Shower Pan 4/19/2024 Partial Approval JUSTIN HAWLEY
Shower Pan 5/2/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 5/9/2024 Approved JUSTIN HAWLEY
Insulation 5/13/2024 Approved JUSTIN HAWLEY
Drywall Nailing 5/15/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 8/12/2024 Approved JUSTIN HAWLEY
Final 8/12/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 8/12/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 8/12/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 8/12/2024 Approved JUSTIN HAWLEY
Final 2/27/2025 OK to Issue CofO LUIS CASTRO