12946-12948 W LEMAY ST 91606

Certificate Information: 12946-12948 W LEMAY ST 91606

Application / Permit
23014-20000-04462
Plan Check / Job No.
B23VN14914
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MAJOR INT/EXT REMODEL WITH IRR SHAPED ADDITIONS AT FRONT & REAR OF EX DWELLING UNIT TO COMBINE & EXPAND KITCHEN/DINING/LIVING RM. AND TO ENLARGE EX BEDRMS. NEW BATHRMS & LAUNDRY RM PER PLAN. NEW FRONT 6'2"X3' PORCH. ONE NEW 1/2 BATHRM (ACCESS FROM OUTSIDE ONLY). CONVERT EXISTING ATT GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22. ALL WORK PER ENGR DESIGN.
Permit Issued
Issued on 12/19/2023
Issuing Office
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/3/2023 HAYATO TSUCHIYA
Corrections Issued 11/4/2023 HAYATO TSUCHIYA
Building Plans Picked Up 11/7/2023 APPLICANT
Applicant returned to address corrections 12/18/2023 LUISANGEL VALENZUELA
Plan Check Approved 12/19/2023 ALEC MOUSAKHANIAN
Issued 12/19/2023 APPLICANT
CofO in Progress 11/13/2024 OGANES TARAKHCHYAN
Permit Finaled 11/15/2024 DANIEL ORRANTE
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/7/2023 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 11/8/2023 GABRIELLA TORRES
Sewer availability Cleared 11/13/2023 GABRIELLA TORRES
Low Impact Development (LID) Cleared 12/8/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 12/11/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/11/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 2/13/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/15/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 3/11/2024 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Approved JOSE AVILA
Footing/Foundation/Slab 3/13/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 4/25/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 5/6/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Partial Approval JOSE AVILA
ELECTRICAL-Rough 5/24/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 5/24/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/24/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 5/24/2024 Approved OGANES TARAKHCHYAN
Sewer 6/3/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/6/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 6/6/2024 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 6/6/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/11/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 6/11/2024 Approved OGANES TARAKHCHYAN
Insulation 6/11/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 6/18/2024 Approved VINCENT HANLEY
Shower Pan 6/18/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/2/2024 Approved OGANES TARAKHCHYAN
Gas Test 8/23/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 11/12/2024 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 11/12/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 11/12/2024 Approved OGANES TARAKHCHYAN