710 E 27TH ST 90011
Certificate Information: 710 E 27TH ST 90011
- Application / Permit
- 23014-20000-04456
- Plan Check / Job No.
- B23VN14906
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND ADDITION TO (N) ADU PER LAMC 12.22 A.33(c) AND (d). All Work per WFPP
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Metro
- Current Status
- Issued on 12/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2023 | EDWIN ESPIN |
| Corrections Issued | 11/6/2023 | EDWIN ESPIN |
| Plan Check Approved | 12/5/2023 | FERNANDO FLORES |
| Issued | 12/5/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2023 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | DAVID LOPEZ |
| Miscellaneous | Cleared | 11/16/2023 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2023 | JEANIE LAM |
| Sewer availability | Cleared | 11/17/2023 | JEANIE LAM |
| Historic Resource Verification | Cleared | 11/28/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 12/1/2023 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 12/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/21/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 9/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 9/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |