4427 1/2 N KATHERINE AVE 91423

Certificate Information: 4427 1/2 N KATHERINE AVE 91423

Application / Permit
23014-20000-04441
Plan Check / Job No.
B23VN14879
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 16' X 5'-6" AND 9'-1" X 14' TO FIRST FLOOR AND 20'-9" X 29'-1" TO SECOND FLOOR AND CONVERT EXISTING DETACHED GARAGE TO NEW (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SELLA BENYAMIN
Corrections Issued 11/14/2023 SELLA BENYAMIN
Quality Review Completed 11/16/2023 STEVEN KIM
Building Plans Picked Up 11/16/2023 APPLICANT
Plan Check Approved 3/15/2024 SELLA BENYAMIN
Issued 3/15/2024 APPLICANT
CofO in Progress 2/3/2025 MISAEL ESPARZA
No Progress 3/12/2025 MISAEL ESPARZA
CofO in Progress 3/12/2025 MISAEL ESPARZA
Permit Finaled 7/29/2025 RUBEN SALAS
CofO Issued 7/29/2025 RUBEN SALAS
Permit Finaled 7/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/17/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 11/17/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/20/2023 EDGAR ALCARAZ
Sewer availability Cleared 11/20/2023 EDGAR ALCARAZ
ZI Cleared 11/20/2023 NELSON RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/19/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 4/9/2024 Partial Approval MISAEL ESPARZA
Sewer 4/16/2024 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 5/2/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/6/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/9/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 8/2/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 8/2/2024 Approved MISAEL ESPARZA
Green Building Rough 8/2/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/2/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 8/2/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/9/2024 Approved MISAEL ESPARZA
Green Building Rough 8/9/2024 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/9/2024 Approved MISAEL ESPARZA
Insulation 8/14/2024 Corrections Issued MISAEL ESPARZA
Shower Pan 8/14/2024 Approved MISAEL ESPARZA
Insulation 8/15/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/15/2024 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 8/23/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/23/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 8/28/2024 Approved MICHAEL CORTEZ
Pre-Inspection 9/13/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/8/2024 Approved MISAEL ESPARZA
Final 11/8/2024 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 11/8/2024 Approved MISAEL ESPARZA
Green Building Final 11/8/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/8/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 11/8/2024 Not Ready for Inspection MISAEL ESPARZA
Final 12/4/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 12/4/2024 Approved MISAEL ESPARZA
Smoke Detectors 12/4/2024 Approved MISAEL ESPARZA
Final 1/3/2025 Corrections Issued JACK KARGODORIAN
Final 1/22/2025 Corrections Issued MISAEL ESPARZA
Final 1/30/2025 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 1/30/2025 Approved MISAEL ESPARZA
Special/Order Compliance 3/5/2025 Approved MISAEL ESPARZA
Special/Order Compliance 3/7/2025 Approved MISAEL ESPARZA
Special/Order Compliance 3/12/2025 Corrections Issued MISAEL ESPARZA
Special/Order Compliance 3/28/2025 Partial Inspection JUAN VALENZUELA
PLUMBING-Final 4/3/2025 Approved MISAEL ESPARZA
Pre-Inspection 4/14/2025 Corrections Issued MISAEL ESPARZA
Special/Order Compliance 5/2/2025 Partial Inspection MISAEL ESPARZA
Special/Order Compliance 7/7/2025 Approved MISAEL ESPARZA