10620 N LAUREL CANYON BLVD 91331

Certificate Information: 10620 N LAUREL CANYON BLVD 91331

Application / Permit
23014-20000-04436
Plan Check / Job No.
B23VN14872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-0" X 20'-0" ADDITION TO THE EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 SERGIO MUNIZ
Corrections Issued 11/1/2023 SERGIO MUNIZ
Building Plans Picked Up 11/6/2023 APPLICANT
Applicant returned to address corrections 12/1/2023 MOHAMMAD ESMAILI
Issued 12/11/2024 APPLICANT
CofO in Progress 3/19/2026 MICHEL ABAJAN
CofO Issued 4/21/2026 RUBEN SALAS
Permit Finaled 4/21/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/6/2023 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 11/27/2023 GABRIELLA TORRES
Sewer availability Cleared 11/27/2023 GABRIELLA TORRES
Low Impact Development (LID) Cleared 1/30/2024 MELINEH AGHAKHABIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/17/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/18/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 7/18/2025 Approved MICHEL ABAJAN
METHANE-Barrier 7/18/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 7/18/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 7/18/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/6/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/6/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 8/6/2025 Approved MICHEL ABAJAN
METHANE-Rough 8/6/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 8/6/2025 Approved MICHEL ABAJAN
Insulation 8/12/2025 Approved KEVIN BERBERYAN
Drywall Nailing 8/14/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 8/29/2025 Approved MICHEL ABAJAN
Final 8/29/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 8/29/2025 Approved MICHEL ABAJAN
HVAC-Final 8/29/2025 Approved MICHEL ABAJAN
PLUMBING-Final 8/29/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 8/29/2025 Approved MICHEL ABAJAN
Final 9/10/2025 Corrections Issued MICHEL ABAJAN
Final 3/18/2026 OK to Issue CofO MICHEL ABAJAN