6904 N COSTELLO AVE 91405
Certificate Information: 6904 N COSTELLO AVE 91405
- Application / Permit
- 23014-20000-04412
- Plan Check / Job No.
- B23VN14794
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE AND CONVERT (E) REAR PATIO TO HABITABLE SPACE, 16'-1" X 4'-6" FRONT ADDITION, 8'-2" X 7'-4" FRONT PORCH, 24'-3" X 12'-5" ADDITION AT REAR W/ 24'-3" X 10'-4" PATIO. NFPA - 13D FIRE SPRINKLER REQUIRED THROUGHOUT. WORK PER ENGINEER. "COMPLY WITH DEPARTMENT ORDER effective date 10/25/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/14/2023
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 10/28/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/30/2023 | APPLICANT |
| Plan Check Approved | 11/14/2023 | ANGELICA MARTINEZ |
| Issued | 11/14/2023 | APPLICANT |
| CofO in Progress | 7/18/2024 | SCOTT SHUSTER |
| CofO Issued | 10/8/2024 | DAVID JAMES |
| Permit Finaled | 10/8/2024 | DAVID JAMES |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/3/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2023 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 11/8/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/8/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2023 | Partial Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 12/19/2023 | Partial Inspection | BRYAN MEYER |
| Underground Mechanical | 12/19/2023 | Partial Inspection | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 12/22/2023 | Approved | SCOTT SHUSTER |
| Underground Mechanical | 12/22/2023 | Approved | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 12/26/2023 | Conditional Approval | DAVID HICKMAN |
| ELECTRICAL-Rough | 1/4/2024 | Not Ready for Inspection | BRYAN MEYER |
| HVAC-Rough | 1/4/2024 | Partial Inspection | SCOTT SHUSTER |
| PLUMBING-Rough | 1/4/2024 | Partial Approval | BRYAN MEYER |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | BRYAN MEYER |
| ELECTRICAL-Rough | 1/8/2024 | Approved | BRYAN MEYER |
| Green Building Rough | 1/8/2024 | Approved | BRYAN MEYER |
| HVAC-Rough | 1/8/2024 | Approved | BRYAN MEYER |
| PLUMBING-Rough | 1/8/2024 | Approved | BRYAN MEYER |
| Deputy Drilled-In Anchors | 1/11/2024 | Partial Approval | BRYAN MEYER |
| Insulation | 1/12/2024 | Approved | BRYAN MEYER |
| Interior/Exterior Lathing | 1/12/2024 | Partial Approval | BRYAN MEYER |
| Drywall Nailing | 1/17/2024 | Approved | BRYAN MEYER |
| Interior/Exterior Lathing | 1/29/2024 | Partial Approval | BRYAN MEYER |
| Shower Pan | 1/29/2024 | Approved | BRYAN MEYER |
| Final | 6/28/2024 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 6/28/2024 | Approved | SCOTT SHUSTER |
| Green Building Final | 6/28/2024 | Partial Inspection | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 6/28/2024 | Partial Inspection | SCOTT SHUSTER |
| Final | 7/11/2024 | Partial Approval | SCOTT SHUSTER |
| Green Building Final | 7/11/2024 | Approved | SCOTT SHUSTER |
| Smoke Detectors | 7/11/2024 | Approved | SCOTT SHUSTER |
| Final | 7/18/2024 | OK to Issue CofO | SCOTT SHUSTER |